Версия от 23:38, 26 февраля 2024; EducationBot (обсуждение | вклад) (Новая страница: «{{Английская Википедия/Панель перехода}} {{Short description|Railway line in Bangladesh}} {{Use dmy dates|date=November 2022}} {{Infobox rail line | box_width = 28em | name = Dhaka–Jessore line | color = | logo = | logo_width = | image = | image_width =...»)
(разн.) ← Предыдущая версия | Текущая версия (разн.) | Следующая версия → (разн.)
Перейти к навигацииПерейти к поиску

Шаблон:Short description Шаблон:Use dmy dates Шаблон:Infobox rail line Dhaka–Jessore line is a 172 km long under construction broad gauge railway. It is being constructed under the Ministry of Railways, Government of Bangladesh. The line will connect the capital of Bangladesh to Jessore via Dhaka District, Narayanganj District, Munshiganj District, Shariatpur District, Madaripur District, Faridpur District, Gopalganj District, Bangladesh, and Narail District. It is a project related to Padma Bridge.[1][2][3]

Project

The railway connection project of Padma Bridge brings the greater regions of Faridpur and northern Jessore of Bangladesh under the railway network. The first phase includes the construction of a 172 km long broad gauge line starts from Dhaka to Jessore. According to the schedule of the authority, the Padma Bridge Rail link project will be completed in 2024. Including the railway related works over the bridge of Padma, the primary estimated budget of the project was Шаблон:BDT. In this project Bangladeshi government is financing Шаблон:BDT, the remaining Шаблон:BDT will be financed by China.[4] Later the budget was increased by Шаблон:BDT.[5]

Route

According to the sources of the project authority, the proposed line starts from Gendaria in Dhaka.[6] It pass through the districts of Narayanganj, Munshiganj, Madaripur, Shariatpur, Faridpur and Gopalganj of Dhaka Division, Narail and end at Jessore of Khulna Division. The route is divided by four sections for the construction process, The first section includes double line of dual gauge railway from Kamalapur to Gandaria. The second section, includes four railway stations, is a 36 km long single broad gauge line from Gandaria to Mawa. The next section, another single broad gauge line, is 42 km long that starts from Mawa and ends to Bhanga Junction. The section has five railway stations. The last section of the project is an 86 km broad gauge single line. From Bhanga to Rupdia, there will be ten railway stations. The Dhaka–Jessore line is a 172 km railway including 22 km viaduct line and the project authority is building 14 railway stations excluding six realigned railway stations.[7]

Planning

The plan of the railway project consists of the construction of a line 11 meter above the ground, a 43 km long loop, bridges and culverts, 30 level crossings and 40 underpasses etc. The project was scheduled to run from 1 January 2016 to 30 June 2024.[8]

Construction

Файл:Construction of Padma Bridge Rail Link Project 13.jpg
Construction of Dhaka–Jessore line in Dhaka

In 2018, the railway construction of this line, covering 40 km on both sides of the river bridge on Padma, began. However, due to the lack of permission, it was not possible to install the railway on the bridge.[9] On 17 July 2022, permission was given to lay railway tracks on the Padma Bridge.[10] As of May 2022, 60% of the construction of 81 km of the line is complete.[5] On 29 March 2023, the laying of the railway track over the Padma bridge over which the line would run was completed.[11] The construction of Bhanga–Jessore section was inaugurated on 10 June 2023.[12]

Trials and operation

On 4 April 2023, after completing 42 km of the line, a train was run from Bhanga to Padma Bridge on a trial basis.[13] Another trial from Gandaria to Mawa was done on 19 August 2023.[14] It is scheduled to open the first section in September 2023[15] and the second section of the line in June 2024.[12]

Stations

Railway stations on the Dhaka–Jessore line are mentioned below:

Phase 1 (44 km)

Phase 2 (42 km)

Phase 3 (86 km)