Версия от 09:27, 3 марта 2024; EducationBot (обсуждение | вклад) (Новая страница: «{{Английская Википедия/Панель перехода}} {{Short description|Nuclear power plant in Argentina}} {{Use dmy dates|date=November 2021}} {{Infobox power station | name = Embalse Nuclear Power Station | name_official = Central Nuclear Embalse | image = Central Nuclear Embalse aerea.JPG | image_caption = | country = Argentina | coordinates = {{coord|32.232|S|64...»)
(разн.) ← Предыдущая версия | Текущая версия (разн.) | Следующая версия → (разн.)
Перейти к навигацииПерейти к поиску

Шаблон:Short description Шаблон:Use dmy dates Шаблон:Infobox power station

The Embalse Nuclear Power Station (Шаблон:Lang-es) is one of three operational nuclear power plants in Argentina. It is located on the southern shore of a reservoir on the Río Tercero, near the city of Embalse, Córdoba, 110 km south-southwest of Córdoba City.

The plant is a CANDU Pressurised Heavy Water Reactor (PHWR). It employs natural uranium (that is, with 0.72% of 235U) and uses heavy water for cooling and neutron moderation. It has a thermal power of 2,109 MWth, and generates 648 MWe of electricity, with a net output of about 600 MWe, supplying nearly 4.5% of the production of the Argentine Interconnection System (2005).

Additionally, Embalse produces the cobalt-60 radioisotope, which is employed in medicine (cancer therapy) and industrial applications. Argentina is one of the largest producers and exporters of this isotope in the world,[1] along with Canada and Russia.

Embalse was started in 1974 and began operation in 1983 (first criticality 13 March 1983, declared commercial 20 January 1984). It was built by an Italian-Canadian consortium formed by AECL, acting as the "turn-key" supplier of the nuclear portion, and Italimpianti, the "turn-key" supplier of the conventional portion.[2]

On 31 December 2015, the plant was taken offline, having completed its first operating cycle of about 30 years.

On 1 September 2016, the plant received the last two of four steam generators, fundamental elements for the life extension of the plant. The plant was reconditioned to deliver power for another 30 years: the replacement of the four steam generators was one of the key steps. [3] The plant was restarted on 4 January 2019,[4] [5] with power upgraded to a gross capacity of 683 MW and 635 MW net.[6]