Английская Википедия:Chūō Shinkansen
Шаблон:Short description Шаблон:Use dmy dates Шаблон:Infobox rail line
The Шаблон:Nihongo is a Japanese maglev line under construction between Tokyo and Nagoya, with plans for extension to Osaka. Its initial section is between Shinagawa Station in Tokyo and Nagoya Station in Nagoya, with stations in Sagamihara, Kōfu, Iida and Nakatsugawa. Following the completion of the Tokyo-Nagoya line, the line will extend to connect stations in Mie, Nara and Osaka. The line is expected to connect Tokyo and Nagoya in 40 minutes, and eventually Tokyo and Osaka in 67 minutes, running at a maximum speed of Шаблон:Convert. About 90% of the Шаблон:Convert line to Nagoya will be tunnels.
The Chuo Shinkansen is the culmination of Japanese maglev development since the 1970s, a government-funded project initiated by Japan Airlines and the former Japanese National Railways (JNR). Central Japan Railway Company (JR Central) now operates the facilities and research. The line is intended to be built by extending and incorporating the existing Yamanashi test track (see below). The trainsets themselves are popularly known in Japan as Шаблон:Nihongo, though there have been many technical variations.
Government permission to proceed with construction was granted on 27 May 2011. Construction of the line, which is expected to cost over ¥9 trillion (approximately Шаблон:To USD billion USD), commenced in 2014. The start date of commercial service is currently unknown, after Shizuoka Prefecture denied permission for construction work on a portion of the route in June 2020.[1] JR Central originally aimed to begin commercial service between Tokyo and Nagoya in 2027, with the Nagoya–Osaka section planned to be completed as early as 2037. Originally, the Nagoya-Osaka section was planned to be completed as late as 2045, but the date was moved up following a loan from the Japanese government.[2]
Development overview
Miyazaki and Yamanashi Test Tracks
Following the opening of the Tokaido Shinkansen between Tokyo and Osaka in 1964, Japanese National Railways (JNR) focused on the development of faster Maglev technology. In the 1970s, a Шаблон:Convert test track for Maglev research and development was built in Miyazaki Prefecture.[3] As desired results had been obtained at the (now former) Miyazaki test track, an 18.4 kilometer test track with tunnels, bridges and slopes was built at a site in Yamanashi Prefecture, between Ōtsuki and Tsuru (Шаблон:Coord). Residents of Yamanashi Prefecture and government officials were eligible for free rides on the Yamanashi test track, and over 200,000 people took part. Trains on this test track routinely achieved operating speeds of over Шаблон:Convert), allowing for a thorough test of the capabilities of the future Chuo Shinkansen.
The track was extended a further Шаблон:Convert along the future route of the Chuo Shinkansen, to bring the combined track length up to Шаблон:Convert. Extension and upgrading work was completed by June 2013, allowing researchers to run tests at top speed over longer periods.[4][5] The first tests on this longer track took place in August 2013.[6][7] JR Central began offering public train rides at Шаблон:Convert on the Yamanashi test track, via a lottery selection, in 2014.[8] The train holds the world record for the fastest manned train on this track.
Routing
The line's route passes through many sparsely populated areas in the Japanese Alps (Akaishi Mountains), but is more direct than the current Tōkaidō Shinkansen route, and time saved through a more direct route was a more important criterion to JR Central than having stations at intermediate population centers. Also, the more heavily populated Tōkaidō route is congested, and providing an alternative route if the Tōkaidō Shinkansen were to become blocked by earthquake damage was also a consideration. The route will have a minimum curve radius of Шаблон:Convert, and a maximum gradient of 4%. This is more than the traditional Shinkansen lines, which top out at 3%.
The planned route between Nagoya and Osaka includes a stop in Nara. In 2012, politicians and business leaders in Kyoto petitioned the central government and JR Central to change the route to pass through their city.[9] The governor of Nara Prefecture announced in November 2013 that he had re-confirmed the Transport Ministry's intention to route the segment through Nara.[10]
JR Central announced in July 2008 that the Chūō Shinkansen would start at Tokyo's Shinagawa Station, citing difficulties in securing land at nearby Tokyo and Shinjuku stations for a maglev terminal.[11]
Plan name | Route between Kofu and Nakatsugawa |
Distance from Tokyo (km) | Construction costs (JPY) from Tokyo | Shortest journey time from Tokyo | |||
---|---|---|---|---|---|---|---|
to Nagoya | to Osaka | to Nagoya | to Osaka | to Nagoya | to Osaka | ||
Plan A | via Kiso Valley | 334 | 486 | 5.63 trillion | 8.98 trillion | 46 minutes | 73 minutes |
Plan B | via Ina Valley (Chino, Ina, Iida) | 346 | 498 | 5.74 trillion | 9.09 trillion | 47 minutes | 74 minutes |
Plan C | under the Japanese Alps and Iida City | 286 | 438 | 5.10 trillion | 8.44 trillion | 40 minutes | 67 minutes |
A JR Central report on the Chuo Shinkansen was approved by a Liberal Democratic Party panel in October 2008, which certified three proposed routes for the Maglev. According to a Japan Times news article, JR Central supported the more direct route, which would cost less money to build than the other two proposals, backed by Nagano Prefecture. The latter two plans had the line swinging up north between Kōfu and Nakatsugawa stations to serve areas within Nagano.[12] In June 2009, JR Central also announced research results comparing the three routes, estimating revenue and travel time, which showed the most favorable being the shortest Plan C, with long tunnels under the Japanese Alps.[13] The Council for Transport Policy for the Ministry of Land, Infrastructure, Transport and Tourism concluded on 20 October 2010 that Plan C would be most cost-efficient.[14] JR Central announced that one station would be constructed in each of Yamanashi, Gifu, Nagano, and Kanagawa Prefectures.[15] On 31 October 2014, Japan's Ministry of Land, Infrastructure, Transport and Tourism approved Plan C for construction.[16] Construction began on 17 December 2014.[17]
Preparatory work at Nagoya station began in 2016.[18] A skyscraper measuring Шаблон:Convert in height was built by JR Central. The structure is named 名古屋駅新ビル ("Nagoya-eki Shin-biru", Nagoya Station new building) and accommodates a station for the maglev trains in its basement area.[19]
Construction schedule and costs
JR Central announced in December 2007 that it planned to raise funds for the construction of the Chuo Shinkansen on its own, without government financing. Total cost, originally estimated at 5.1 trillion yen in 2007,[20] escalated to over 9 trillion yen by 2011.[21] Nevertheless, the company has said it can make a pre-tax profit of around 70 billion yen in 2026, when the operating costs stabilize.[22] The primary reason for the project's huge expense is that most of the line is planned to run in tunnels (about 86% of the initial section from Tokyo to Nagoya will be underground)[23] with some sections at a depth of Шаблон:Convert (deep underground) for a total of Шаблон:Convert in the Tokyo, Nagoya and Osaka areas.Шаблон:Citation needed
The original construction schedule from 2013, which called for the Tokyo–Nagoya segment to open in 2027 and the Nagoya–Osaka segment to open in 2045, was designed to keep JR Central's total debt burden below its approximate level at the time of privatization (around 5 trillion yen).[24] The schedule was later altered to bring forward the completion date of the Nagoya-Osaka segment to 2037, after JR Central received a loan from the Japanese government.[2]
The first major contract announced was for a Шаблон:Cvt tunnel in Yamanashi and Shizuoka prefectures expected to be completed in 2025.[25] Construction of a Шаблон:Cvt tunnel under the southern Japanese Alps commenced on 20 December 2015, approximately Шаблон:Cvt below the surface at its deepest point. The tunnel is expected to be completed in 2025, and upon completion will succeed the Шаблон:Cvt deep Daishimizu Tunnel on the Joetsu Shinkansen line as the deepest tunnel in Japan. Construction has also started on the maglev station at Shinagawa.[26] Being built below the existing Shinkansen station, and to consist of two platforms and four tracks, construction is planned to take 10 years, largely to avoid disruption to the existing Tokaido Shinkansen services located above the new station.
JR Central estimates that Chuo Shinkansen fares will be only slightly more expensive than Tokaido Shinkansen fares, with a difference of around 700 yen between Tokyo and Nagoya, and around 1,000 yen between Tokyo and Osaka. The positive economic impact of the Chuo Shinkansen in reducing travel times between the cities has been estimated at anywhere between 5 and 17 trillion yen during the line's first fifty years of operation.[27]
Shizuoka Prefecture dispute
Construction is yet to commence on the part of the line going through Shizuoka Prefecture, as the municipality has expressed concern about water from the Ōi River leaking into the tunnel, lowering the water level.[28] JR Central expressed concern early on that the delay in construction of the only 9 kilometer long section going through Shizuoka might throw the entire project off schedule.[29]
It is believed by some political analysts that the actual reason for Shizuoka Prefecture's apparent concerns of the project is not over the Ōi River, but was merely used as a pretense to force JR Central's hand in building a train station on the Tokaido Shinkansen under Shizuoka Airport.[30] Shizuoka Prefecture, being the only prefecture where no new station will be built, has long lobbied JR Central for years for the construction of such a station, with the line running directly under the airport. The railway has so far refused, citing the close distance to the neighboring Kakegawa Station and Shizuoka stations. If constructed, travel time from the center of Tokyo to the airport would be comparable to that for Tokyo Narita Airport, enabling it to act as a third hub airport for the capital.[31] As the station would be built underneath an active airport, it is expected to open after the new maglev line.[32]
Officials of Shizuoka Prefecture, in a meeting with JR Central in June 2020, denied permission to begin construction work on the tunnel. JR Central announced the following week that it would be "difficult" to open the Tokyo-Nagoya line in 2027 as previously announced.[1] The incumbent governor of Shizuoka Prefecture Heita Kawakatsu was re-elected in June 2021, partly on a platform of continued opposition to construction of the new line, barring further accommodations by JR Central.[33]
Following a series of meetings between JR Central and Shizuoka Prefecture facilitated by the Ministry of Transportation, an interim report was released on the results of the meetings so far in late December 2021. Among other things, the report confirmed that while JR was committed to returning any water leaking into the tunnel once construction was completed, there is no known feasible way to return all of the water during the construction phase. However, it did also conclude that the amount of water leaked was likely to be insignificant.[34]
On 7 January 2022, commenting on the report, the Shizuoka Prefecture governor expressed continued opposition to construction when it could result in water levels going down, even if only during construction. He urged JR Central to re-investigate the possibility of returning leaking water during construction.[35] On 20 January that same year, the prefecture officially called the report "insufficient", and announced that it still would not allow construction to commence.[36]
On 21 December 2023, during a routine press conference, JR Central’s President Niwa announced an agreement with Tokyo Electric Power Company, the Ōi River's dam operator, to diminish the volume of water extracted from the upstream dam. This action aims to address the anticipated impact on the Oi River’s water levels, a consequence of the construction project. The agreement outlines the method of reducing water intake and the concept of compensation. The proposal was well-received and endorsed previously by the local governing council in November 2023.Шаблон:Cn
Osaka extension
The government of Osaka Prefecture, as well as local corporations such as Suntory and Nippon Life, have raised concerns about the impact of the delayed construction of the Nagoya–Osaka segment on the Osaka economy. Politicians from the Kansai region called for, and received, state-backed loans for JR Central in order to expedite the line's construction, resulting in the opening of the extension being moved forward by up to 8 years.[10]
Construction accidents
On 27 October 2021, two construction workers died when part of the retaining wall of a temporary work tunnel collapsed. JR Central concluded that the safety checks carried out were insufficient, and vowed to make it clearer to workers which areas had and had not completed the safety checks necessary to allow for the presence of human workers going forward.[37]
Route
Шаблон:GeoGroup The line will run between Tokyo and Nagoya, with plans for extension to Osaka. Its initial section is between Shinagawa Station in Tokyo and Nagoya Station in Nagoya, with stations in Sagamihara, Kōfu, Iida, and Nakatsugawa.[38] The line has one station for each prefecture it passes through, except for Shizuoka. The line is expected to connect Tokyo and Nagoya in 40 minutes, and eventually Tokyo and Osaka in 67 minutes, running at a maximum speed of Шаблон:Convert.[15]
About 90% of the Шаблон:Convert line to Nagoya will be in tunnels,[39] with a minimum curve radius of Шаблон:Cvt and a maximum grade of 4% (1 in 25).
Technology
Шаблон:Main The Chūō Shinkansen will employ the SCMaglev technology, a maglev (magnetic levitation train) system developed by JR Central. The levitating force is generated between superconducting magnets on the trains and coils on the track.[41] The absence of wheel friction allows higher speed and higher acceleration and deceleration than conventional high-speed rail.[41]
The superconducting coils use Niobium–titanium alloy cooled to a temperature of Шаблон:Convert with liquid helium.[41] Magnetic coils are used both for levitation and propulsion. The trains are accelerated by alternating currents on the ground producing attraction and repulsion forces with the coils on the train. The levitation and guidance system, working with the same principle, ensures that the train is elevated and centered in the track.[41]
Energy consumption
In 2018, a scientific comparison of the energy consumption of SCMaglev, Transrapid and conventional high-speed trains was conducted. The energy consumption per square meter of usable area was examined in relation to speed.[42] The results show that there are only minor differences at speeds of 200 km/h and above. However, maglevs can reach much higher speeds than conventional trains. Conventional trains, on the other hand, require less energy at slow speeds, with this advantage shrinking or even slightly reversing during high-speed operation. As the Chūō Shinkansen mostly runs in tunnels, air resistance will be much higher than for most high-speed railways, significantly increasing energy consumption.[42]
During normal operating conditions, the energy consumption of the L0 series between Tokyo and Osaka is estimated at 90-100 Wh/seat-km. For comparison, the conventional N700-series train operating on the fastest service-pattern on the existing line between Tokyo and Osaka has an estimated energy consumption of 70 Wh/seat-km.[42]
Despite this increase, the L0 series still consumes much less energy than even the most efficient short/medium-haul modern passenger aircraft. For instance, the Airbus A319neo uses ~209 Wh/seat-km over a distance of 1,900 km. This figure would presumably be even higher for very short flights such as Tokyo-Nagoya, with much less time spent cruising.[43] Moreover, the operation of the L0 series maglev train is completely electric, making it easier to transition to renewable energy sources.
Rolling stock
On 2 December 2003, MLX01, a three-car train set a world record speed of Шаблон:Convert in a manned run. On 16 November 2004, it also set a world record for two trains passing each other at a combined speed of Шаблон:Convert.
On 26 October 2010, JR Central announced a new train type, the L0 Series, for commercial operation at Шаблон:Convert.[44] It set a world record speed for a manned train of Шаблон:Convert on 21 April 2015.[45]
On 26 March 2020, the Improved L0 Series started operations on the test track. It represents the completion of 80–90% of the design goals for the final train, and is the first to draw power from the track. Previous models used on-board gas generators.
See also
References
External links
- JR Central information about the Chuo Shinkansen
- JR Central's website for the Linear-Express service Шаблон:In lang
- Linear Chuo Express Шаблон:In lang
- SCMAGLEV Website Шаблон:Webarchive
- SCMaglev at International Maglev Board Шаблон:Webarchive
Шаблон:Shinkansen Шаблон:JRШаблон:Tokyo transitШаблон:Osaka transitШаблон:Maglev
- ↑ 1,0 1,1 Ошибка цитирования Неверный тег
<ref>
; для сносокkyodo03Jul20
не указан текст - ↑ 2,0 2,1 Шаблон:Cite news
- ↑ Шаблон:Cite journal Шаблон:Subscription required
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite magazine
- ↑ Johnston, Eric, "Economy, prestige at stake in Kyoto-Nara maglev battle", The Japan Times, 3 May 2012, p. 3.
- ↑ 10,0 10,1 Шаблон:Cite news
- ↑ Шаблон:Cite news Шаблон:Dead link
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ 15,0 15,1 Kyodo News, "JR Tokai to list sites for maglev stations in June", The Japan Times, 2 June 2011, p. 9.
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ JR東海、リニア新幹線建設を全額自己負担 総事業費5.1兆円 Шаблон:Webarchive, IB Times, 26 December 2007 Шаблон:In lang
- ↑ Шаблон:Cite news
- ↑ JR Tokai to build maglev system, The Japan Times, 26 December 2007
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Citation
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Citation
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite magazine
- ↑ Шаблон:Cite web
- ↑ 41,0 41,1 41,2 41,3 Шаблон:Cite web
- ↑ 42,0 42,1 42,2 Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ http://www.mlit.go.jp/common/000145486.pdf Шаблон:Bare URL PDF
- ↑ Шаблон:Cite web
- Английская Википедия
- Страницы с неработающими файловыми ссылками
- High-speed railway lines in Japan
- Shinkansen
- Proposed railway lines in Japan
- Railway test tracks
- 2027 in rail transport
- High-speed railway lines under construction
- Страницы, где используется шаблон "Навигационная таблица/Телепорт"
- Страницы с телепортом
- Википедия
- Статья из Википедии
- Статья из Английской Википедии
- Страницы с ошибками в примечаниях