Шаблон:Short description Шаблон:Infobox road The Cross Bronx Expressway is a major freeway in the New York City borough of the Bronx. It is mainly designated as part of Interstate 95 (I-95), but also includes portions of I-295 and U.S. Route 1 (US 1). The Cross Bronx begins at the Alexander Hamilton Bridge over the Harlem River, where the Trans-Manhattan Expressway continues west across Upper Manhattan to the George Washington Bridge. While I-95 leaves at the Bruckner Interchange in Throgs Neck, following the Bruckner Expressway and New England Thruway to Connecticut, the Cross Bronx Expressway continues east, carrying I-295 to the merge with the Throgs Neck Expressway near the Throgs Neck Bridge. Though the road goes primarily northwest-to-southeast, the nominal directions of all route numbers west of the Bruckner Interchange are aligned with the northbound route number going southeast, and the southbound route number going northwest.

The Cross Bronx Expressway was conceived by Robert Moses and built between 1948 and 1972. It was the first highway built through a crowded urban environment in the United States; the most expensive mile of road ever built to that point is part of the Cross Bronx, costing $40 million (Шаблон:Inflation). At one point during construction, Moses' crews had to support the Grand Concourse (a major surface thoroughfare), a subway lineШаблон:Efn and several elevated train linesШаблон:Efn while the expressway was laboriously pushed through. The highway experiences severe traffic problems, and its construction has been blamed for negatively affecting a number of low-income neighborhoods in the South Bronx.[1]

Route description

Файл:Cross Bronx Expressway time-lapse.webm
A time-lapse video of a westbound trip on the Cross Bronx Expressway and adjacent highways

The Cross Bronx Expressway begins at the eastern end of the Alexander Hamilton Bridge as a continuation of the Trans-Manhattan Expressway and officially designated as both I-95 and US 1. Immediately after coming off the bridge, there is an interchange with the Major Deegan Expressway (I-87) for Yankee Stadium and points upstate. The highway soon intersects with Webster Avenue at a partial interchange allowing eastbound vehicles to exit and westbound ones to enter. Northbound US 1 leaves the Cross Bronx Expressway at this exit. About Шаблон:Convert later, the expressway has a pair of closely spaced interchanges for New York State Route 895 (NY 895, Sheridan Boulevard) and the Bronx River Parkway. The exit for Sheridan Boulevard is an incomplete interchange and allows access from northbound and to southbound I-95 only.[2]

The Cross Bronx Expressway reaches the Bruckner Interchange Шаблон:Convert later. The service road is called East 177th Street between the Bronx River Parkway and the Bruckner Interchange.[3] Going eastbound (I-95 northbound), the interchange allows access to southbound I-678, northbound I-95 (Bruckner Expressway) and southbound I-295. I-95 leaves the Cross Bronx Expressway here and continues north along the Bruckner Expressway. The Cross Bronx Expressway continues east of the interchange as I-295, which begins here.[2] The Cross Bronx ends Шаблон:Convert later at the Throgs Neck Expressway, where traffic from I-695 merges on toward the Throgs Neck Bridge.[4]

History

Planning

Файл:CBX Parkchester 6 jeh.JPG
Eastward from Westchester Avenue

The 1929 Report on Highway Traffic Conditions and Proposed Traffic Relief Measures for the City of New York was the first citywide traffic study, classifying a number of projects that had been proposed by local interests. A "Cross-Bronx Route" along 161st and 163rd Streets was one of two proposed facilities, along with the "Nassau Boulevard" (which became the Long Island Expressway), picked by borough engineers as examples of important projects.[5] Although this routing was south of the present Cross Bronx Expressway, the report did suggest a "New Cross-Bronx Artery" near the present expressway that would link the Washington Bridge with the Clason Point Ferry to Queens. Though it would not be built to freeway standards, it would be 60 feet (18 m) wide with grade separations "where considered necessary and desirable." The George Washington Bridge, then under construction, was cited among reasons to build the highway which would help connect New Jersey to Long Island via the bridges and ferry.[6]

In 1936, the Regional Plan Association (RPA) proposed a highway that would connect the Bronx to New England and points north.[7] In late 1940, the New York City Planning Commission adopted a plan for a network of highways. Except for the Bronx and Pelham Parkway, which lay to the north, no cross-Bronx highway had been built up to this point.[8] The report stated that the "Bronx Crosstown Highway", which would now connect on the east end to the Bronx–Whitestone Bridge (which had replaced the Clason Point Ferry), was "an essential part of a desirable highway pattern", taking traffic from the George Washington Bridge to Long Island and New England. The cost was estimated at $17 million, higher than most improvements because of the "topographical conditions, high land values, and heavily built-up areas".[9]

Construction

Файл:CBX 174 GC jeh.JPG
The Expressway traverses beneath Walton Avenue and Grand Concourse.

In the 1940s, city planner Robert Moses proposed the construction of a system of highways that would traverse the New York City area.[10] The plan was to cost $800 million (equivalent to $Шаблон:Formatprice in Шаблон:Inflation/yearШаблон:Inflation/fn), and, in February 1945, the city agreed to pay $60 million (equivalent to $Шаблон:Formatprice in Шаблон:Inflation/yearШаблон:Inflation/fn) of that cost.[11] That November, the city, state, and federal governments agreed to fund several new highways in New York City. Among these was the Cross Bronx Expressway, which was to cost $38.67 million.[12] The expressway was to continue onto the 181st Street Bridge at its western end, connecting with the 178th–179th Street Tunnels and the George Washington Bridge via a set of ramps.[13] At its eastern end, the expressway would connect with the Hutchinson River Parkway and New England Thruway at the Bruckner Interchange.[14]

The New York City Board of Estimate approved a contract in February 1946, allowing the Tenant Relocation Bureau to relocate 540 families who lived on the expressway's right-of-way.[15] The New York City Council adopted a resolution the next month, asking the Board of Estimate to delay the relocations,[16] which were scheduled to start that June.[17] City officials said that only 55 families would be relocated in 1946 and that all existing residents would be relocated before construction started.[18][19] By late 1947, the city and state governments were relocating residents in the expressway's path.[20] The city and state started soliciting bids for construction contracts that December.[20][21] Although the city and state planned to demolish 164 structures on the expressway's right-of-way, they were reluctant to raze all of the structures immediately because of a housing shortage in New York City.[22]

Construction of the expressway began in 1948.[23][24] A 112-foot open cut was excavated, accommodating six Шаблон:Convert traffic lanes and four Шаблон:Convert cobblestone shoulders. This project proved to be one of the most difficult expressway projects at the time; construction required blasting through ridges, crossing valleys and redirecting small rivers. In doing so, minimal disruption to the apartment buildings that topped the ridges in the area of Grand Concourse was a priority.[25] Moreover, the expressway had to cross 113 streets, seven expressways and parkways (some of which were under construction), as well as numerous subway and train lines.[25][26] The highway also passed by hundreds of utility, water and sewer lines, none of which could be interrupted.[25][27] The highway was to contain 54 bridges and three tunnels when it was completed.[27] By early 1949, the project's budget had increased to $53 million,[28] in part because of material shortages.[22][28]

Eastern section

By early 1949, the first section of the expressway, between Olmstead Avenue and Westchester Creek, was not planned to be completed until 1951.[29] The Gull Construction Company was contracted to build this segment in May 1949,[30] and Rusciano & Sons was hired the same month to build the footings for six bridges along the expressway.[31] In addition, Frederick H. Zurmuhlen was supervising the construction of a bridge over Westchester Creek at a cost of $5,287,000;[32] the ten-lane bridge was to supplement a surface-level span.[33] Engineering firms Andrews & Clark and Hardesty & Hanover were hired to supervise the project later in 1949.[34] A short segment near Bruckner Boulevard opened in 1950 and was the first part of the expressway to be completed.[35]

The state government hired the J. Kaufman Demolition Company in 1951 to raze structures on the right-of-way east of the Bronx River Parkway.[36] By early 1953, part of the highway east of the Bronx River Parkway was also being constructed.[14] The construction of this section required excavating underneath the Parkchester station of the New York City Subway's Pelham Line.[35] In addition, the Bronx River had to be relocated several hundred feet in the vicinity of the Bronx River Parkway interchange.[27][26] The section from the Bronx River Parkway to the Bruckner Interchange opened on November 5, 1955, at the same time as parts of the Queens Midtown and Major Deegan expressways. The first portion of the Cross Bronx Expressway had cost $34.6 million and was about Шаблон:Convert long.[37][38] The segment was six lanes wide;[39] its original western end was at Rosedale Avenue, where ramps connected to the northbound Bronx River Parkway.[40] A one-mile (1.5 km) western extension from the Bronx River Parkway to a temporary interchange at Longfellow Avenue, near Boston Road, opened on April 23, 1956.[41]

When the Throgs Neck Bridge to Queens opened on January 11, 1961,[42][43] the Cross Bronx was extended east as one of the bridge's two northern approaches, the other being the Throgs Neck Expressway (later I-695). Both extensions were part of the Interstate Highway System.[44] The Cross Bronx Expressway Extension and the Clearview Expressway were originally designated as part of I-78,[45][46][47] which was to continue through Queens, Brooklyn, and Manhattan to the Holland Tunnel.[48][49][50] Ultimately, most of I-78 was canceled in 1971.[51][52][46] In anticipation of this change, the Cross Bronx Expressway Extension and the Clearview Expressway were renumbered I-295 on January 1, 1970.[53]

Central section

The section of the Cross Bronx Expressway between Anthony and Longfellow Avenues was highly controversial.[54] In early 1953, Bronx borough president James J. Lyons proposed relocating the Cross Bronx Expressway near Crotona Park in order to preserve 1,000 houses in the expressway's right-of-way. Under Lyons's plan, the highway would curve slightly southward and run along the northern edge of Crotona Park, creating a "kink" in the routing.[55][56] Moses, who called Lyons's proposal "unreasonable", threatened to resign from his position as city construction coordinator if Lyons's alternative was approved.[57][58] Moses also threatened to cancel federal funding for the entire project.[59] After an acrimonious public hearing in April 1953, the Board of Estimate could not agree on whether to relocate the expressway along Crotona Park.[60] State officials supported Moses's original plan, saying that the Crotona Park alternative would create "curves and reverse curves of sub-standard radius".[54] Ultimately, the Board of Estimate approved Moses's original alignment that May.[61][62]

By 1954, the project's cost had increased to $86 million, but land for the western section of the expressway had not even been purchased, leading The New York Times to describe the existing sections as a "road to nowhere".[35] Although the Cross Bronx Expressway had been one of the first highways planned in New York City, it was estimated that the expressway would be the last project to be completed.[63] In November 1954, the Board of Estimate voted unanimously to buy land for the section between Anthony and Longfellow Avenues, despite continued opposition from Bronx residents. At the time, officials estimated that the central section of the expressway would cost $21 million.[64][65] Of this cost, $8 million would be spent on acquiring the land and relocating 1,462 families.[65] By 1956, the Times reported that the center section was not expected to be completed for several years because of the expense of relocating tenants.[66]

Construction of the section between exits 3 and 2B began in early 1958, at which point the project's total cost had increased to $101 million. The most expensive part of the project was the Шаблон:Convert segment between exits 2B and 2A in Tremont, Bronx, which was planned to cost $11.788 million; it included a Шаблон:Convert tunnel under the Grand Concourse and the underground Concourse Line, as well as an open cut that passed under five avenues.[67] On April 27, 1960, another 1.2-mile (2 km) piece opened, taking the road west to Webster Avenue.[68][69] Later that year, the westernmost Шаблон:Convert of the expressway was closed to allow the completion of the Tremont section.[70] The 0.6-mile (1 km) Tremont segment from Webster Avenue west to Jerome Avenue opened on February 10, 1961.[71][72] By that time, all construction contracts for the remaining sections of the expressway had been awarded.[72]

Western section

Файл:CBX Deegan junction jeh.JPG
Deegan interchange

The 181st Street Bridge, and the ramps from the bridge to the existing 178th Street Tunnel and a new 179th Street Tunnel in Manhattan, were originally part of the Cross Bronx Expressway.[13] In 1949, workers began widening the 181st Street Bridge, constructing the ramps, and excavating the 179th Street Tunnel.[73][74] The widening was finished by 1950,[75][76] and the tunnel and interchange opened on May 5, 1952.[77][78] Originally, there had not been any plans to construct an interchange with the Major Deegan Expressway, at the highway's western end, because of the area's steep topography and limited space.[79] In December 1952, the city and state reached an agreement to finance the construction of an interchange at that site.[79][80]

Plans for the western end of the expressway were modified substantially[81] after the Port Authority of New York and New Jersey announced in 1957 that it would construct a lower deck on the George Washington Bridge.[82] To accommodate the additional traffic from the George Washington Bridge, the Trans-Manhattan Expressway and Alexander Hamilton Bridge were to be constructed, connecting the George Washington Bridge and the Cross Bronx Expressway.[83][84] The revised plans were announced in 1958. At the time, the Alexander Hamilton Bridge was planned to be completed in 1962, but the interchange with the Major Deegan would not open until two years after that.[81] With the opening of the Alexander Hamilton Bridge in April 1963, the $128 million Cross Bronx was completed, but two major interchanges were still incomplete: the Highbridge Interchange with the Major Deegan Expressway (I-87), and the Bruckner Interchange with the Bruckner Expressway (I-95/I-278), the Hutchinson River Parkway, and the Bronx–Whitestone Bridge (I-678).[85]

Later modifications

The $12.6 million Highbridge Interchange opened in November 1964.[86][87] The $68 million reconstruction of the Bruckner Interchange, allowing Bruckner Expressway traffic to bypass the old traffic circle, opened on January 2, 1972.[88][89] (Cross Bronx traffic passing through to the Throgs Neck Bridge had been able to avoid the circle, but drivers taking the Bruckner in either direction, including those bound for New England, had to exit onto the surface.)[90]

Effects

Urban decay

Файл:Cross Bronx Expressway.jpg
Congestion

The Cross Bronx Expressway is blamed for worsening the decay of neighborhoods in the South Bronx, such as Tremont. In Robert Caro's The Power Broker, the author argues that Moses intentionally directed the expressway through this neighborhood, even though there was a more viable option only one block south.[91] The expressway's construction displaced many residents, who generally were not relocated to adequate housing.[92] The New York Times reported in 2022 that the areas near the Cross Bronx Expressway were among New York City's poorest neighborhoods; these areas contained 220,000 residents, most of which were ethnic minorities.[93]

Many of the neighborhoods it runs through have been continually poor since its construction, partly due to the lowered property value caused by the expressway.[93] This is partially responsible for the public opposition to many other planned expressways in New York City that were later cancelled – in particular, the Lower Manhattan Expressway,[94] and may have provided impetus to Jane Jacobs, an American expatriate, in her opposition to the Scarborough Expressway in Toronto. Architect Ronald Shiffman argues that the Cross Bronx Expressway "ripped through the heart of the Bronx, creating what was a wall between what eventually was known as the Northern and Southern part of the Bronx."[95]

Health issues

The Cross Bronx Expressway accounts for a large proportion of the Bronx's roadway pollution.[96][97] Bronx residents are more likely to have asthma than residents of other boroughs, and a large portion of those are children. Because things like dust, pollution, and other allergens serve as factors for developing asthma, children of color living in low-income areas in the Bronx are at risk of suffering from asthma exacerbation. Asthma rates in the Bronx are three times higher than the national average.[96] In the Morris Heights neighborhood of the West Bronx, where the Cross Bronx and Major Deegan Expressways intersect, air-pollution rates are also generally higher than in the rest of the borough.[97] To decrease emissions from the Cross Bronx Expressway, community activists proposed constructing a freeway lid in the early 2020s.[98][99]

Congestion

The expressway is one of the main routes for shipping and transportation through New York City due to its connections with New Jersey via the George Washington Bridge, Long Island via the Throgs Neck and Whitestone Bridges, Upstate New York via I-87 northbound and the Bronx River Parkway, Manhattan via I-87 southbound to the Robert F. Kennedy Bridge or the Trans-Manhattan Expressway (extension of the Cross Bronx Expressway westward) and the Henry Hudson Parkway, and New England via the New England Thruway (I-95) and the Hutchinson River Parkway. As such, the expressway is also known for its extreme traffic problems; in 2000, nearly 180,000 vehicles used the Cross Bronx's six lanes every day.[100] It is not uncommon for truckers to use the Cross-Westchester Expressway to the New York State Thruway and the Major Deegan Expressway to get around this stretch of I-95. Proposals have been made to make dedicated truck lanes, add express bus service, and build decking on the open trenches to allow for parks, although to no avail.[101]

In both 2008 and 2007, Inrix cited the Cross Bronx Expressway's westbound exit 4B (Bronx River Parkway) as being the worst intersection in the United States. In 2008, the expressway's exits included three out of the top four on the list, and four of the top five in 2007.[26][102] Congestion is often exacerbated by the fact that large portions of the Cross Bronx Expressway does not meet modern Interstate standards,[103] as well as the relative lack of arterial roads between the West Bronx and East Bronx.[104] Large portions of the expressway do not have shoulders, so even minor breakdowns could cause congestion.[103][104] A 2002 study by the New York State Department of Transportation found that the expressway also had short entrance and exit ramps, poor sightlines, and dim lighting.[100][104] Other issues were caused by the fact that the expressway's service roads were discontinuous, forcing traffic onto the expressway or local streets.[104]

In 2022, the Metropolitan Transportation Authority released an environmental impact statement, which detailed the possible impacts of a planned congestion pricing zone in New York City. The study found that, if the zone were implemented, up to 700 additional trucks per day would use the Cross Bronx Expressway to avoid the congestion pricing zone.[93][105]

Exit list

Two separate exit numbering systems are used on the Cross Bronx Expressway. West of the Bruckner Interchange, the expressway uses I-95's mileage-based exit numbers, which increase from west to east. East of the Bruckner Interchange, the expressway uses I-295's sequential exit numbers, which increase from east to west. Шаблон:NYinttop Шаблон:Jctint Шаблон:Jctbridge Шаблон:NYCint Шаблон:NYCint Шаблон:NYCint Шаблон:Jcttunnel Шаблон:NYCint Шаблон:NYCint Шаблон:Jcttunnel Шаблон:NYCint Шаблон:NYCint Шаблон:NYCint Шаблон:Jcttunnel Шаблон:NYCint Шаблон:NYCint Шаблон:NYCint Шаблон:NYCint Шаблон:NYCint Шаблон:NYCint Шаблон:NYCint Шаблон:NYCint Шаблон:Jctbtm

Notes

Шаблон:Notelist

References

Шаблон:Reflist

External links

Шаблон:Attached KML

  1. Berman, Marshall. "All That is Solid Melts Into Air." New York: Penguin: 1988
  2. 2,0 2,1 Ошибка цитирования Неверный тег <ref>; для сносок Google не указан текст
  3. Шаблон:Cite act Шаблон:Webarchive
  4. New York City Department of Transportation, Truck Routes Шаблон:Webarchive, accessed November 2007: shows that the Cross Bronx Expressway Extension ends at the Throgs Neck Expressway, while the Throgs Neck Expressway continues to the Throgs Neck Bridge
  5. Шаблон:Cite news
  6. Harland Bartholomew, Report to the Honorable James J. Walker, Mayor, on Highway Traffic Conditions and Proposed Traffic Relief Measures for the City of New York, Day & Zimmermann, 1929, OCLC 35914068
  7. Шаблон:Cite news
  8. Шаблон:Cite map
  9. Шаблон:Cite news
  10. Шаблон:Cite news
  11. Шаблон:Cite news
  12. Шаблон:Cite news
  13. 13,0 13,1 Шаблон:Cite news
  14. 14,0 14,1 Шаблон:Cite news
  15. Шаблон:Cite news
  16. Шаблон:Cite news
  17. Шаблон:Cite news
  18. Шаблон:Cite news
  19. Шаблон:Cite news
  20. 20,0 20,1 Шаблон:Cite news
  21. Шаблон:Cite news
  22. 22,0 22,1 Шаблон:Cite news
  23. Шаблон:Cite news
  24. Шаблон:Cite news
  25. 25,0 25,1 25,2 Шаблон:Cite Power Broker
  26. 26,0 26,1 26,2 Шаблон:Cite web
  27. 27,0 27,1 27,2 Шаблон:Cite news
  28. 28,0 28,1 Шаблон:Cite news
  29. Шаблон:Cite news
  30. Шаблон:Cite news
  31. Шаблон:Cite news
  32. Шаблон:Cite news
  33. Шаблон:Cite news
  34. Шаблон:Cite news
  35. 35,0 35,1 35,2 Шаблон:Cite news
  36. Шаблон:Cite news
  37. Шаблон:Cite news
  38. Шаблон:Cite news
  39. Шаблон:Cite news
  40. Шаблон:Cite news
  41. Шаблон:Cite news
  42. Шаблон:Cite web
  43. Шаблон:Cite news
  44. Шаблон:Cite news
  45. Шаблон:Cite news
  46. 46,0 46,1 Шаблон:Cite book
  47. Шаблон:Cite map
  48. Шаблон:Cite map
  49. Шаблон:Cite journal
  50. Шаблон:Cite news
  51. Шаблон:Cite news
  52. Шаблон:Cite web
  53. Шаблон:Cite book
  54. 54,0 54,1 Шаблон:Cite news
  55. Шаблон:Cite news
  56. Шаблон:Cite news
  57. Шаблон:Cite news
  58. Шаблон:Cite news
  59. Шаблон:Cite news
  60. Шаблон:Cite news
  61. Шаблон:Cite news
  62. Шаблон:Cite news
  63. Шаблон:Cite news
  64. Шаблон:Cite news
  65. 65,0 65,1 Шаблон:Cite news
  66. Шаблон:Cite news
  67. Шаблон:Cite news
  68. Шаблон:Cite news
  69. Шаблон:Cite news
  70. Шаблон:Cite news
  71. Шаблон:Cite news
  72. 72,0 72,1 Шаблон:Cite news
  73. Шаблон:Cite news
  74. Шаблон:Cite news
  75. Шаблон:Cite news
  76. Шаблон:Cite news
  77. Шаблон:Cite news
  78. Шаблон:Cite news
  79. 79,0 79,1 Шаблон:Cite news
  80. Шаблон:Cite news
  81. 81,0 81,1 Шаблон:Cite news
  82. Шаблон:Cite news
  83. Шаблон:Cite news
  84. Шаблон:Cite news
  85. Шаблон:Cite news
  86. Шаблон:Cite news
  87. Шаблон:Cite news
  88. Шаблон:Cite news
  89. Шаблон:Cite news
  90. Шаблон:Cite map
  91. Шаблон:Cite book
  92. The Cross-Bronx Double Cross: How the cross-Bronx ... - Fordham University. (n.d.). Retrieved October 30, 2022, from https://research.library.fordham.edu/cgi/viewcontent.cgi?article=1019&context=amer_stud_theses Шаблон:Webarchive
  93. 93,0 93,1 93,2 Шаблон:Cite news
  94. Ric Burns, New York: A Documentary Film, episode 7, The American Experience, PBS Television, WNET New York and WGBH Boston, 1999.
  95. Шаблон:Cite web
  96. 96,0 96,1 The Cross-Bronx Double Cross: How the cross-Bronx ... - Fordham University. (n.d.). Retrieved October 30, 2022, from https://research.library.fordham.edu/cgi/viewcontent.cgi?article=1019&context=amer_stud_theses Шаблон:Webarchive
  97. 97,0 97,1 Шаблон:Cite web
  98. Шаблон:Cite web
  99. Шаблон:Cite web
  100. 100,0 100,1 Шаблон:Cite news
  101. Шаблон:Cite web
  102. Шаблон:Cite news
  103. 103,0 103,1 Шаблон:Cite news
  104. 104,0 104,1 104,2 104,3 Шаблон:Cite web
  105. Шаблон:Cite web