Английская Википедия:Eastern HVDC

Материал из Онлайн справочника
Перейти к навигацииПерейти к поиску

Шаблон:Short description Eastern HVDC and Eastern HVDC projects are the names used by Ofgem for two planned HVDC submarine power cables from the East coast of Scotland to Northeast England to strengthen the National Grid. The two links combined will deliver 4Шаблон:NbspGW of renewable energy from Scottish wind farms to England.

Ofgem state that "At an estimated cost of £3.4Шаблон:Nbspbillion for the two links, the Eastern HVDC projects would be the largest electricity transmission investment project in the recent history of Great Britain."[1]

Eastern HVDC projects

Файл:Route map of cables for Eastern HVDC projeccts.jpg
Ofgem's schematic map of cables for Eastern HVDC projects

In July 2022, Ofgem published its conditional decision on the Final needs case for the Eastern HVDC project, confirming its choice of two separate HVDC links, each rated at 2Шаблон:NbspGW.[1]

  • Scotland-England Green Link 1 (SEGL1) will run from Torness in Southeast Scotland to Hawthorn Pit substation in county Durham
  • Eastern Green Link 2 (EGL2) is will run from Peterhead, near Aberdeen, to Drax in Yorkshire

Ofgem approved the schemes as part of its Accelerated Strategic Transmission Investment Framework.[2]

Scotland-England Green Link 1 (SEGL1)

Current status

In December 2022, the connection received approval from the UK energy regulator Ofgem.[2] [3] As of July 2021, construction was expected to start in 2023, with the construction phase complete in 2027.[4]

Route

SEGL1 will run from Torness in Southeast Scotland to Hawthorn Pit substation in Northeast England.[5] Landfall in England will be to the North of Seaham, on the Durham Coast.[4]

Technical specification

The cable will carry 2Шаблон:NbspGW.[3] The DC voltage will be +/-525Шаблон:NbspkV, using voltage source converter (VSC) technology, carried on cross-linked polyethylene (XLPE) cables, with a fall back option of mass impregnated (MI) cables.[1]

Economic case

The investment required is £1.294Шаблон:Nbspbillion.[1]

Project partners

SEGL1 is being developed by Scottish Power Transmission plc (SPT) and National Grid Electricity Transmission plc (National Grid).[5]

Eastern Green Link 2 (EGL2)

Current status

In December 2022, the connection received approval from the UK energy regulator Ofgem.[2]

As of December 2022, the project was in the "early development" stage.[5] Early enabing works are expected in 2024, with the main construction phase starting in 2025. Target date for energisation is 2029.[3]

Route

The cable will run from Sandford Bay, at Peterhead in Scotland, to the Drax Power Station in Yorkshire, England. The northern converter station will be next to the existing power station at Peterhead. [3][5] The subsea portion of the cable will be approximately Шаблон:Convert long, from the Aberdeenshire coast to the East Riding of Yorkshire.[6]

Technical specification

The cable will carry 2Шаблон:NbspGW.[3] The DC voltage will be +/-525Шаблон:NbspkV, using Voltage Source converter (VSC) technology, carried on Cross-linked polyethylene (XLPE) cables, with a fall back option of mass impregnated (MI) cables.[1]

Economic case

The investment required is £2.1Шаблон:Nbspbillion. It is needed to reinforce the National Grid, to "alleviate existing and future constraints on the electricity transmission network", and support new renewable electricity generation.[3]

Project partners

EGL2 is a joint venture between SSEN Transmission and National Grid Electricity Transmission (NGET).[3]

See also

Шаблон:Portal Western HVDC Link

References

Шаблон:Reflist

External links