According to planning from 2015 to 2021, this entire expressway used to be part of the North-South Expressway[1] before being separated into an independent expressway (only the Long Thành - Lộ 25 section still belongs to this system). However, in reality, this expressway is still denoted as CT.01 on some signposts of this expressway. This expressway is part of the AH1 system (section of Lộ 25 - Long Trường).
Construction
Construction
The project was started on October 3, 2009 with a scale of 4 lanes and a total length of 55.7 km.[2] The investor is Vietnam Expressway Development Investment Corporation (VEC) with total investment in phase I: 997.67 million USD ((equivalent to 20,630 billion VND) [3].The project is sponsored by the Asian Development Bank (ADB) and the Japan International Cooperation Agency (JICA).
Complete
About 20 km out of a total of 55 km of the expressway, the section from Ring Road 2 to National Highway 51 in Dong Nai province was opened to traffic on 2 January, 2014.[4].On 29 August, 2014, Ring Road 2 intersection opened to traffic. The 4 km long road from An Phu intersection, Mai Chi Tho Avenue to Ring Road 2 intersection opened to traffic on 10 January, 2015. All The expressway opened to traffic on 2 February, 2015, when the 31 km long Long Thanh - Dau Giay section completed construction.
Extend
Currently, Vietnam Expressway Development Investment Corporation (VEC) is researching investment in expanding the section from Ring Road 2 intersection to the intersection with Bien Hoa - Vung Tau Expressway, 21.92 km long, from 4 to 8 - 10 lanes, total investment is about 14,786 billion VND.
Design
The expressway has a total length of 55.7 km and is divided into two sections:
An Phú-Ring Road II section: 4 km long, designed according to urban road standards, design speed 80 km/h; Phase 1 scale: four lanes, roadbed width 26.5 m, road surface width 2×7.5 m and emergency stop lane width 2×3 m.