The Boten–Vientiane railway is the Lao section of the Laos–China Railway (LCR), running between the capital Vientiane and the northern town of Boten on the border with Yunnan, China. The line was officially opened on 3 December 2021.[1]

A collaborative project between Laos and China, the line's northern end is directly connected to the Chinese rail system at Mohan in Yunnan, through the Yuxi–Mohan railway, and has provisions in the south to link up with the Bangkok–Nong Khai high-speed railway in Thailand and possibly all the way to Singapore via HSR. The railway ends at Vientiane South cargo station. The Boten–Vientiane railway is an integral section of the central line on the Kunming–Singapore railway,[2] and was constructed as part of the Belt and Road Initiative (BRI).[3][4]

History

Planning

Laos is the only landlocked country in Southeast Asia, which burdens it with a competitive disadvantage in trade.[5] During French rule, the French failed to develop a plan to build railways in Laos, with only the Шаблон:Cvt Don Det–Don Khon railway being completed.[6] A railway link from China through Laos would greatly reduce cargo transit times and transportation costs between the two countries.[5]

The first talks about the railway linking Laos and China began in 2001. A Lao politician of Chinese descent, Somsavat Lengsavad, was reportedly the driving force behind the project on the Laotian side. In October 2010, plans were announced for a Шаблон:Convert standard gauge railway linking Vientiane to Xishuangbanna, in Yunnan province in China.[7][8] Construction was expected to begin in 2011, for completion in 2014.[9][10] There are plans to extend this railway south, from Vientiane across the Thai border to Bangkok.[11]

The project initially stalled in the wake of the 2011 corruption scandal involving China's minister of railways, Liu Zhijun, but negotiations continued. In November 2012, the Laotian press reported that the money for the construction of the railway would be borrowed from the Export–Import Bank of China,[12] and construction would be started in 2013 and completed in 2018.[7] By 2015, a revised plan was agreed upon, under which both countries would jointly finance and operate the railway with a build-operate-transfer arrangement.[13] Construction work worth US$1.2 billion was awarded to the China Railway Group in September 2015.[13]

Construction and completion

Construction began at Luang Prabang on 25 December 2016.[14] At the end of 2017, the construction phase was 20% completed,[15] and in September 2019 progress was reported as 80% completed.[16] Unexploded bombs that have been dropped during the Vietnam War would also be removed along the route.[17]

Шаблон:As of, Chinese state media reported that the US$6 billion project was 90% complete. Work crews started laying track in Laos in March 2020, five years after breaking ground. With all of the hundreds of tunnels, bridges and viaducts completed, cargo service was scheduled to start from December 2021.[18] In April 2021, the northernmost section in Luang Namtha Province was 97% complete. Track laying of the last section in Oudomxay Province would be completed in May, leaving the project well on track for a 2021 opening.[19] Track-laying was officially completed on 12 October 2021.[20] The first EMU was delivered to Vientiane on 16 October 2021, and the line opened on 3 December 2021, a day after the 46th anniversary of the Lao PDR.[1][21]

The railway is expected to boost tourism, with passenger traffic to account for the majority of traffic on the line.[4][22] The Thai province of Nong Khai is also expected to gain more visitors through the railway, as well as fruit exports from Thailand to China benefiting from reduced transportation costs.[23]

As of 2024, it is the most significant Belt and Road Initiative project in Laos.[24]Шаблон:Rp

Future expansion

Since the line uses a different rail gauge from the existing Thai Northeastern Line link from Bangkok to Thanaleng, running into Thailand is not yet possible for passenger trains. A branch to Thanaleng Dry Port freight yard was completed in July 2022, allowing transfer of cargo between Thai metre gauge railway and Laos standard gauge railway.

However, the Vientiane end of the line will eventually cross the Mekong River on a new bridge to meet up with the Bangkok–Nong Khai high-speed railway once it is completed, making the connection.[25] As of 2023, the design of this extension is in progress with a target completion date of 2028.[26]

Financing

Файл:Luang Prabang railway station.jpg
Luang Prabang Station

The cost of the project is estimated at US$5.965 billion[27] or RMB 37.425 billion.[28] The railway is 60% funded with debt financing ($3.6 billion) from the Export–Import Bank of China, and the remaining 40% ($2.4 billion) by a joint venture company between the two countries, in which China holds a 70% stake. Of the remaining 30%, the Laotian government disburses $250 million from its national budget and borrows $480 million further from the Export–Import Bank of China.[29] It is the most expensive and largest project to be constructed in Laos as of 2021.[30]

The cost of the railway has contributed to a US$480 million increase in Lao debt to the Export–Import Bank of China. Western publications subsequently claimed that Laos could end up falling into a default on its debts.[31][29][32] In 2019, the Australian think-tank Lowy Institute estimated Laos' debt to China at 45% of its GDP.[31] In 2020, American credit agency Fitch Ratings assigned Laos a 'CCC' credit rating, stating that the country has "excessive debt".[30]

Файл:Laos-China-Railway Station Vientiane.jpg
Vientiane train station

Ridership

Between January 2021 and December 2021, the Laos–China Railway as a whole transported over 1 million passengers and 500,000 tonnes of cargo, according to the transport authorities of Yunnan Province.[33]

Infrastructure

Файл:Bridge construction in Luang Prabang Province 2.jpg
Bridge construction in Luang Prabang Province
Файл:中国ラオス鉄道.jpg
Viaduct under construction near Vientiane

47% of the railway is spanned over 75 tunnels and 15% is set on viaducts spread over 167 bridges.[13][14] Vientiane railway station, the largest station on the railway, is situated in Xay Village in Xaythany District and consists of four platforms with seven track lines and two additional platforms with three lines reserved; it is expected to connect with other railway lines planned for Laos. The station can accommodate up to 2,500 passengers with a total area of 14,543 square metres.[34]

The railway is built on a single track with passing loops and is electrified to China's Class I trunk railway standards, suitable for Шаблон:Cvt passenger and Шаблон:Cvt freight trains, making Laos the first country to connect to the Chinese high-speed railway network using Chinese technology.[22]

Rolling stock

Файл:Laos-China-Railway.jpg
A high-speed train carriage, with bilingual signage in Laotian and Chinese

Passenger services employ CR200J trainsets, and for freight hauling, HXD3CA locomotives are used.[35][36][37]

Cargo

On 4 December 2021, a day after opening the China–Laos railway, the Vientiane Logistics Park, one of a total of nine logistics centres in Laos, was officially opened by Prime Minister Phankham Viphavanh at Thanaleng.[38]

List of stations

32 stations are planned along the line,[39] of which 21 stations were initially constructed, including 10 passenger stations and 11 cargo stations:[40][41][42]

Station name Station type km [43] Cumulated travel time Fast Train Cumulated travel time Ordinary Train
Boten Passenger 000 00h00 00h00
Na Teuy Passenger, major 013 00h09 00h11
Na Moh Passenger 028 no stop 00h26
Na Thong Cargo 038 no stop no stop
Muang Xai Passenger, major 067 00h39 00h57
Na Khok Cargo 097 no stop no stop
Muang Nga Passenger 113 no stop 01h34
Huoay Han Cargo 135 no stop no stop
Luang Prabang Passenger, major 168 01h31 02h15
Xiang Ngeun Cargo 177 no stop no stop
Phou Khoun Cargo 209 no stop no stop
Kasi Passenger 239 no stop 03h04
Pha Daeng Cargo 256 no stop no stop
Vang Vieng Passenger, major 283 02h31 03h41
Vang Khi Cargo 310 no stop no stop
Phon Hong Passenger 342 no stop 04h23
Phon Soung Cargo 372 no stop no stop
Vientiane North Cargo 388 no stop no stop
Vientiane Passenger, major 406 03h35 05h15
Vientiane South Cargo 419 no stop no stop

Controversies

Radio Free Asia reported in October 2021 that some Lao villagers displaced from their land by the line's construction complained that they had still not received compensation.[44]

In the first year of operation, the railway only allowed ticket purchases up to three days in advance and online sales were not available. That resulted in extremely long lines at ticket offices, and express trains often sold out the day ticket sales opened.[45] This has since been partially ameliorated with the LCR mobile app, which allows online purchase of tickets; albeit only for users with a Laotian phone number and still only for three days in advance.

See also

References

Шаблон:Reflist

External links

Шаблон:Kunming–Singapore railway Шаблон:One Belt, One Road

  1. 1,0 1,1 Шаблон:Cite web
  2. Шаблон:Cite web
  3. Шаблон:Cite web
  4. 4,0 4,1 Шаблон:Cite web
  5. 5,0 5,1 Шаблон:Cite web
  6. Шаблон:Cite web
  7. 7,0 7,1 Laos-China railways ready to roll, 2012-11-16
  8. Шаблон:Cite web
  9. Шаблон:Cite web
  10. Шаблон:Cite web
  11. Шаблон:Cite web
  12. Шаблон:Cite web
  13. 13,0 13,1 13,2 Шаблон:Cite web
  14. 14,0 14,1 Шаблон:Cite news
  15. Шаблон:Cite web
  16. Шаблон:Cite web
  17. Шаблон:Cite web
  18. Шаблон:Cite web
  19. Шаблон:Cite web
  20. Ошибка цитирования Неверный тег <ref>; для сносок trackcompleted не указан текст
  21. Ошибка цитирования Неверный тег <ref>; для сносок thestar202111 не указан текст
  22. 22,0 22,1 Шаблон:Cite web
  23. Шаблон:Cite web
  24. Шаблон:Cite book
  25. Шаблон:Cite news
  26. https://www.thestar.com.my/aseanplus/aseanplus-news/2023/12/18/high-speed-rail-linking-thailand039s-nong-khai-and-laos-capital-vientiane-expected-to-complete-in-2028
  27. Шаблон:Cite web
  28. Шаблон:Cite web
  29. 29,0 29,1 Шаблон:Cite web
  30. 30,0 30,1 Шаблон:Cite web
  31. 31,0 31,1 Шаблон:Cite web
  32. Шаблон:Cite web
  33. Шаблон:Cite web
  34. Шаблон:Cite news
  35. Шаблон:Cite web
  36. Шаблон:Cite web
  37. Шаблон:Cite web
  38. The Ambassador of Timor-Leste in Vientiane: Thanaleng Dry Port International Border Checkpoints was officially inaugurated by H.E. Mr. Phankham Viphavanh, Prime Minister of Laos. Thanaleng Dry Port is located at prime location with an extensive area of 382 hectares, and granted the exclusive privilege by the Lao government, as a flagship to drive the national logistics strategy to transform Laos from a landlocked into a land linked country. Thanaleng and Vientiane Logistic Park project is one of the 9 Dry ports in Laos., 4 December 2021, retrieved 4 December 2021.
  39. Шаблон:Cite web
  40. Шаблон:Cite webШаблон:Dead link
  41. Шаблон:Cite web
  42. Шаблон:Cite web
  43. Шаблон:Cite web
  44. Шаблон:Cite news
  45. Шаблон:Cite web