Английская Википедия:Callide Power Station

Материал из Онлайн справочника
Перейти к навигацииПерейти к поиску

Шаблон:Short description Шаблон:Use Australian English Шаблон:Use dmy dates Шаблон:Infobox power station Callide Power Station is an electricity generator at Mount Murchison, Shire of Banana, Queensland, Australia. It is coal powered with eight steam turbines with a combined generation capacity of 1,720 megawatts (MW) of electricity. Callide A was commissioned in 1965, refurbished in 1998 and decommissioned in 2015/16.[1] As of 2018, generation capacity was 1510 MW.[1]

The coal for Callide comes from the nearby Callide Coalfields and water from the Awoonga dam and Stag Creek Pipeline.[2]

An explosion and fire at the Callide C power plant in late May 2021 caused a significant power outage that affected over 375,000 premises and raised electricity prices for weeks afterwards.

November 2022 all four units at the coal-fired Callide Power Station were not operating after a structural failure at the cooling plant brought the C3 unit offline, and later on the B2 unit tripped during scheduled testing, followed by the last unit, B1, also tripping.[3][4]

Callide A

Файл:Premier Frank Nicklin opening Callide Power Station, Biloela, 21 August 1965.jpg
Premier Frank Nicklin opening Callide Power Station, 21 August 1965

At the end of 1962 approval was granted for a new power station near Biloela.[5] Work commenced at the site in February 1963. The design of the plant based around separate generating units and a control room was a first for Queensland.[5] It was also the first power station in Queensland to use dry cooling towers.[5]

Файл:Callide Oxyfuel Project.jpg
Callide Oxyfuel Project, 2012

It had four 30 MW steam turbines, the first of which was operating by June 1965. From its commissioning a drought meant water restrictions at the station reduced output.[5] The second set was expected to be operating by May 1966, but was lost at sea while being transported from England.[5] A replacement unit arrived in June 1967. The third set was operating in October 1967 and the fourth in May 1969.[5] The total cost of the project was A$28.7 million.[5]

Callide A has been in storage since 2001, except for Unit 4 which was being used for the Callide Oxyfuel project.[6] The Callide Oxyfuel project was decommissioned in 2015/16 after demonstrating carbon capture technology for two years.[1]

Callide B

Following on from an aggressive construction program at Tarong Power Station, Callide B was commissioned in 1988 with two 350 MW steam turbines. The Hitachi machines are almost identical to those in Tarong and Stanwell.

In October 2019, Federal Energy Minister Angus Taylor announced that Callide B's originally planned 2038-39 closure was being brought forward to 2028.[7]

Callide C

The Callide Power Plant (a.k.a. Callide C) was commissioned in 2001 with two 405 MW advanced cycle steam turbines.[8] Callide C uses a more efficient "supercritical" boiler technology to burn coal to generate electricity.[9] It was built to operate to 2050.[10]

Carbon Monitoring for Action estimates this power station emits 5.73 million tonnes of greenhouse gases each year as a result of burning coal.[11] The Australian Government introduced a Carbon Pollution Reduction Scheme in 2011 to help combat climate change, intended to reduce emissions from power stations. The scheme was replaced in 2014 by a 'direct action' program. The National Pollutant Inventory provides details of other pollutant emissions, but, as at 23 November 2008, not CO2.[12]

On 25 May 2021, an explosion and subsequent fire at Callide C caused a significant power outage (including Callide B and parts of Stanwell and Gladstone power stations)[13] that affected over 375,000 premises,[14][15][16] and caused increased power prices for weeks.[17] The hydrogen-filled generator had a catastrophic failure, resulting in significant damage. Despite speculation that the plant would close, it will be repaired at an estimated cost of $200M and hoped to be completed by December 2022.[18][19][10] As at November 2022, the expectation completion is oct 2023.[20][21]

See also

Шаблон:Portal

References

Шаблон:Reflist

External links

Шаблон:EnergyQueensland