Шаблон:Infobox dam Daram Khola-A Hydropower Station (Шаблон:Lang-ne) is a run-of-the-river hydroelectricity plant located in Baglung District of Nepal. The flow from Daram River is used to generate 2.5 MW electricity.

Location and hydrology

The Daram Khola-A Hydropower Station is on the Daram Khola (Daram River). The catchment area of the intake is Шаблон:Convert. The design discharge is Шаблон:Convert with a maximum net head of Шаблон:Convert.Шаблон:Sfn Two other projects on the river were under construction in 2020, the 3 MW mid-Daram A and 4.5 MW mid-Daram B.Шаблон:Sfn

The weir of the hydroelectric project is in the Hila and Argal village development committees of the Baglung District. The powerhouse is in Argal VDC on the left bank of the Daram Khola. It can be reached from Baglung Bazar by a Шаблон:Convert road, of which Шаблон:Convert is gravel and the rest dirt.Шаблон:Sfn

Technical

Headworks structures include a weir across the river, intake, desander, gravel trap, surge tank/forebay and spill-way.Шаблон:Sfn From the headworks a Шаблон:Convert penstock pipe with diameter Шаблон:Convert carries water to the powerhouse.Шаблон:Sfn The surface powerhouse has two horizontal Francis turbines with rated discharge of Шаблон:Convert feeding synchronous 3-phase generators with rated output of 1350 KW each.Шаблон:Sfn

Construction

Design of the project was undertaken by Innovative Engineering Services (IES) of Nepal under contract to Dhaulagiri Civil Electrical Mechanical Engineering.Шаблон:Sfn The Initial Environmental Examination report for the project was submitted for approval to the Department of Electricity Development on 23 February 2012.Шаблон:Sfn In December 2012 it was reported that construction had begun and was expected to cost Rs. 460 million and to take two years.Шаблон:Sfn Commercial production of electricity began on 26 May 2016.Шаблон:Sfn

Finance

The plant is owned and developed by Sayapatri Hydropower Pvt. Ltd., an Independent Power Producer of Nepal. The plant started generating electricity from 2073-03-12BS.[1] The generation licence will expire in 2105-02-01 BS, after which the plant will be handed over to the government.[2] The power station is connected to the national grid and the electricity is sold to Nepal Electricity Authority.[3] The company is going to Issue IPO to raise fund . The company has appoint Laxmi capital as issue manager . [1]