Delhi–Amritsar–Katra Expressway is an approved Шаблон:Convert long, 4-lane (expandable to 8 lanes) wide controlled-access expressway, which will connect Bahadurgarh border near Delhi with Katra in Jammu and Kashmir via Haryana and Punjab.[1][2] It will have a spur section which will connect Nakodar with Sri Guru Ram Dass Jee International Airport located in Raja Sansi, Amritsar.[3] The Шаблон:Convert long Delhi–Nakodar–Katra section is National Expressway 5 (NE-5) and Шаблон:Convert long Amritsar–Nakodar section is National Expressway 5A (NE-5A). Once completed, it will reduce the current Delhi-Katra distance from Шаблон:Convert to Шаблон:Convert and the time travel will be reduced from 14 hours to 6 hours, and Delhi-Amritsar distance to Шаблон:Convert and from the time travel will be reduced from 8 hours to only 4 hours.[3]

It will have a trauma centre, ambulances, fire brigades, traffic police, bus bays, truck stops, interchanges with refreshment, and recreational facilities. To be constructed as a part of the Bharatmala Pariyojana,[1] it is expected to cost 40,000 crores.[4] Detailed Project Report (DPR) was completed in November 2019,[5] and land acquisition commenced from January 2020.[6][7] M/S Feedback Infra Pvt Ltd. was appointed as DPR consultant to carry out alignment studies which submitted the final shortest proposed alignment report of Delhi–Nakodar–Gurdaspur section in September 2019,[8] Nakodar–Amritsar section in June 2020, and the survey is currently under progress in Jammu section.[9] It is part of Ludhiana-Delhi-Kolkatta Industrial Corridor. There are 11 National industrial corridors and numerous state level industrial corridors in India.

Файл:11 Industrial Corridors.png
11 National Industrial Corridors of India.

Project details

It is a combination of greenfield and which brownfield expressway which passes through Haryana, Punjab, and Jammu and Kashmir. It starts from Kundli Manesar Palwal (KMP) Expressway near Nilothi village in Jhajjar District. It will lessen the workload of Grand Trunk Road. The Ministry of Road Transport and Highways of the NDA government planned to construct 10 expressways in the country under Bharatmala Pariyojana, one of which would connect the national capital Delhi with Katra and Amritsar via Kharkhoda, Jind, Sangrur, Malerkotla, Ludhiana, Jalandhar, Gurdaspur.

The Greenfield expressway splits into two near Nakodar. One greenfield section towards Amritsar would pass nearby Sultanpur Lodhi, Goindwal Sahib, Khadoor Sahib, TarnTarn and ends near Sri Guru Ram Dass Jee International Airport.[10] The second section goes straight to Katra, bypassing Kathua and Jammu, and it consists of both greenfield and brownfield parts. Central and state governments also agreed to connect Dera Baba Nanak and Kartarpur Corridor with this expressway project. Nearly 14,000 acres of the land of Punjab and 5,000 acres of Haryana will be acquired for the construction of this expressway.

Construction

The NHAI has divided the construction work of Delhi–Amritsar–Katra Expressway into 2 Phases with a total of 21 construction packages.

Phase 1

Sr. No. Package Segment Length Contractor
1. Nilothi (Jhajjar)–Rukhi Pana (Sonipat) Шаблон:Convert KCC Buildcon[11]
2. Rukhi Pana (Sonipat)–Gangana (Sonipat) Шаблон:Convert CDS Infra Projects[11]
3. Gangana (Sonipat)–Alewa (Jind) Шаблон:Convert KCC Buildcon[11]
4. Alewa (Jind)–Kharak Pandwa (Kaithal) Шаблон:Convert NKC Projects[12]
5. Kharak Pandwa (Kaithal)–Ghagga (Patiala) Шаблон:Convert CDS Infra Projects[12]
6. Ghagga (Patiala)–Bhawanigarh (Sangrur) Шаблон:Convert Shiv Build India[13]
7. Bhawanigarh (Sangrur)–Bhogiwal (Malerkotla) Шаблон:Convert Ceigall India[14]
8. Bhogiwal (Malerkotla)–Mullanpur Dakha (Ludhiana) Шаблон:Convert Evrascon – MKCIL JV[14]
9. Mullanpur DakhaNakodarKang Sahbu Шаблон:Convert Evrascon – MKCIL JV[12]
10. Kang Sahbu (Jalandhar)–Khojewal (Kapurthala) Шаблон:Convert Evrascon – MKCIL JV[13]
11. Khojewal (Kapurthala)–Sri Hargobindpur Шаблон:Convert Evrascon – MKCIL JV[15]
12. Sri HargobindpurGurdaspur Шаблон:Convert Evrascon – MKCIL JV[16]

Nakodar–Amritsar spur

Sr. No. Package Segment Length Contractor
1. Nakodar (Jalandhar)–Dhunda (Tarn Taran) Шаблон:Convert SP Singla Constructions
2. Dhunda (Tarn Taran)–Manawala Khurd (Tarn Taran) Шаблон:Convert Ceigall India[15]
3. Manawala Khurd (Tarn Taran)–Harsha Chhina (Amritsar) Шаблон:Convert Vozrozhdenie India[13]

Phase 2

Sr. No. Package Segment Length Contractor
13. Details awaited Шаблон:Convert Tender Notice pending
14. Balsua (Gurdaspur)–Gurah Baildaran (Kathua) Шаблон:Convert Megha Engineering & Infrastructures
15. Gurah Baildaran (Kathua)–Jakh (Samba) Шаблон:Convert Vishwa Samudra Engineering
16. Jakh (Samba)–Jammu Airport Шаблон:Convert Shivalaya Construction Company
17. Details awaited Шаблон:Convert Apco Infratech
18. Details awaited Шаблон:Convert Gawar Construction

Route alignment

Delhi to Nakodar (Main route)

The Phase-1 of Delhi–Amritsar–Katra Expressway consists of two sections, namely DelhiNakodarGurdaspur (NE-5) and NakodarAmritsar (NE-5A). The Phase-2 consists of GurdaspurKatra section. Following is the alignment agreed by the Governments of Haryana, Punjab, and Jammu and Kashmir with the NHAI.[7][17][3]

Haryana

Alignment is from Nilothi-Kharkhoda-Gohana(west)- Jind(east)-Safidon(west)-Ratoli(Ambala-Narnaul)-Assandh(west)-Kalayat-Kaithal(west)-Barta. There is a proposal to extend it in Delhi from nilothi to "Urban Extension Road II".

Punjab

Nakodar to Amritsar (Spur-1)

First greenfield expressway spur (99 km long) from Nakodar to Amritsar through Sultanpur Lodhi, Goindwal Sahib, Khadur Sahib, Tarn Taran Sahib and ends at Sri Guru Ram Dass Jee International Airport (Amritsar Airport).

Punjab

Nakodar to Katra (Spur-2)

Second greenfield expressway spur from Nakodar to Katra passing through Kartarpur, Gurdaspur, and Dinanagar.

Punjab

Jammu and Kashmir

Inter-connectivity

Following provide the inter-connectivity:

Status updates

  • Nov 2019: DPR of Delhi-Amritsar-Katra expressway completed by NHAI.[5]
  • Jun-Jul 2020: In Haryana, Punjab, and Jammu and Kashmir, the land acquisition process started.[6][7][20][9]
  • Apr 2021: Construction work awarded by NHAI for all 12 packages on 397.7 Km long Delhi-Nakodar-Gurdaspur section, and 2 out of 3 packages on 99 km long Nakodar-Amritsar section.
  • Sep 2021: NHAI announces the completion deadline is by October 2023.[21]
  • December 2023: The whole expressway will be completed by end of 2025, though various subsections will be progressively opened earlier than that.[25]