Gorakhpur Link Expressway is an under-construction Шаблон:Cvt long, 4-lane wide (expandable to 6) expressway in the Indian state of Uttar Pradesh. It will connect Jaitpur village on NH-27 in Gorakhpur district with Salarpur village on Purvanchal Expressway in Azamgarh district.[1] Salarpur village is situated near Kalwari Bagh interchange (NH-135A).

It was launched in 2018 by Chief Minister Yogi Adityanath and land acquisition was started in February 2019 by the Government of Uttar Pradesh.[2] The total project value of Gorakhpur Link Expressway, including the land acquisition cost is around ₹ 5,876 crores.[1][3]

Route

The Gorakhpur Link Expressway will connect Jaitpur village on Gorakhpur Bypass in Gorakhpur district with Salarpur village (south of Jalalpur) on Purvanchal Expressway in Azamgarh district.[1] It will pass through 4 districts of Uttar Pradesh i.e. Gorakhpur, Sant Kabir Nagar, Ambedkar Nagar and Azamgarh.

Construction

The construction cost (excluding the cost of Land) is around 3,024 crores. Around Шаблон:Convert of land will be acquired for this project.[4][5] 2 Toll Plaza, 3 ramp plaza, 7 Flyovers, 7 major bridges, 27 minor bridges, 16 vehicular-underpasses (VUP), 50 Light VUP and 35 pedestrian underpasses will also be constructed.

The construction work of the 91.352 km long Gorakhpur Link Expressway is divided into 2 packages:

Sr. No Package Length in km Contractor
1. Jaitpur (Gorakhpur)–Fulwariya (Ambedkar Nagar) 48.317 Apco Infratech
2. Fulwariya (Ambedkar Nagar)–Salarpur (Azamgarh) 43.035 Dilip Buildcon Limited[6]

Status updates

  • Feb 2019: Land acquisition work started by Government of Uttar Pradesh.[2]
  • Oct 2019: 50% of the required land has been acquired. Construction work is divided in 2 packages.[7]
  • Nov 2019: Dilip Buildcon Ltd receives Letter of Acceptance (LoA) for Package-2 on 29 November 2019.
  • Feb 2020: Construction work started on 10 February for Package-1 by Apco Infratech.
  • Apr 2020: Road construction work resumed.[8]
  • Jun 2020: Construction work started on 19 June for Package-2 by Dilip Buildcon.[9]
  • Mar 2021: 1,044 out of 1,095 Hectares (95.36%) of required land has been acquired till 30 March.
  • Jun 2021: 24% of construction work and 50% of earthwork is completed as of 28 June.[10]
  • Aug 2021: 27.4% of construction work completed as of 16 August, 2021.[11]
  • Nov 2021: 29% of construction work completed as of 8 November, 2021.[12]
  • Jan 2022: 50% of the earthwork and 34% of construction work has been completed.[13]
  • April 2022: As of 25 April, 39.57% of overall construction work including 65% of earthwork and 265 out of 339 structures have been completed.
  • May 2022: 69% of earthwork and 45% of overall construction work has been completed. 282 structures out of 339 have been completed.
  • July 2022: 71% of earthwork and 49% of overall construction work has been completed. 286 structures out of 342 have been completed.
  • August 2022: 75% of earthwork and 52% of overall construction work has been completed. 289 structures out of 342 have been completed.
  • March 2023: 62% of overall construction work has been completed, 319 structures out of 342 have been completed. and is now confirmed to become operational by December 2023.[14]
  • September 2023: 96% of earthwork and 81% of overall Construction work has been completed, 336 structures out of 341 have been completed.