Английская Википедия:Gwynt y Môr
Шаблон:Infobox power station Шаблон:Maplink
Шаблон:Langnf is a 576-megawatt (MW) offshore wind farm located off the coast of north Wales and is the fifth largest operating offshore windfarm in the world. The farm has 160 wind turbines of Шаблон:Convert tip height above mean sea level.[1]
Planning consent for the project was granted on 3 December 2008. The project has a value of 2 billion Euros, of which 1.2 billion Euros were spent on turbines and electrical connections. Construction began in 2012, power production started in September 2013, construction phase ended in November 2014, and final commissioning occurred in June 2015.[2]
In May 2020 plans to add up to 107 new turbines were submitted to Flintshire Council, increasing the windfarm by an extra 41 square miles, with a generating capacity of at least 100 megawatts.[3]
Design and planning
As with all offshore wind farms in the UK the Crown Estate[4] owns the seabed at Gwynt y Môr. It has agreed to lease the land to RWE npower renewables. The wind farm is located close to the existing North Hoyle and Rhyl Flats offshore wind farms. These projects are wholly or partly owned by RWE npower renewables, a subsidiary of German company RWE. In the case of Gwynt y Môr, RWE holds 50%, Stadtwerke München holds 30%, Siemens holds 10% and UK Green Investment Bank holds 10%.[5]
With 160 turbines[6] of 3.6MW Siemens SWT-3.6-107, Gwynt y Môr will be Wales' largest wind farm. The output of 1,950 GWh per year is capable of powering around 400,000 homes, or 30% of the homes in Wales. This prevents the release of about 1.7 million tonnes of carbon dioxide every year.[6][7]
Planning consent for the project was granted on 3 December 2008.[8] The project has a value of 2 billion Euros. 1.2 billion Euros will go to Siemens for turbines and electrical connections.
Two floating experimental LIDAR wind measurement stations have been tested at the site for two years.[9]
Construction
Construction work began offshore in January 2011 when pieces of rock were laid on softer parts of the seabed to secure the foundations of the turbines.[10] Work began on laying undersea cables from the windfarm to the shore in August 2012.[11] The project uses four 132 kV subsea cables manufactured by NKT.[12] In order to feed electricity into the national grid, a substation was built near St Asaph in Denbighshire.[11]
Power production started in September 2013.[13] Final commissioning was completed on 18 June 2015.[2][14]
Its levelised cost has been estimated at £179/MWh.[15]
See also
- Wind power in the United Kingdom
- List of offshore wind farms
- List of offshore wind farms in the United Kingdom
- List of offshore wind farms in the Irish Sea
- npower (UK)
References
External links
- Gwynt y Môr Шаблон:Webarchive, RWE Innogy
Шаблон:Wind power in the United Kingdom Шаблон:Energy in Wales Шаблон:RWE
Шаблон:EngvarB Шаблон:Use dmy dates
- ↑ Шаблон:Cite web
- ↑ 2,0 2,1 windpoweroffshore.com, David Weston, UK: RWE has completed the construction phase of the 576MW Gwynt y Mor project ahead of final commissioning next year Шаблон:Webarchive, 24 November 2014
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ greeninvestmentbank.com 31 March 2014: UK Green Investment Bank invests £461m in the UK offshore wind sector Шаблон:Webarchive
- ↑ 6,0 6,1 RWE Innogy, Stadtwerke München and Siemens build offshore wind farm Gwynt y Môr
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Weston, David. "Lidar test completed at Gwynt y Mor Шаблон:Webarchive" Windpower offshore, 20 February 2015. Accessed: 25 February 2015.
- ↑ Шаблон:Cite news
- ↑ 11,0 11,1 Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite journal
- Английская Википедия
- Offshore wind farms in the Irish Sea
- Wind farms in Wales
- RWE
- Round 2 offshore wind farms
- 2015 establishments in Wales
- Energy infrastructure completed in 2015
- Страницы, где используется шаблон "Навигационная таблица/Телепорт"
- Страницы с телепортом
- Википедия
- Статья из Википедии
- Статья из Английской Википедии