Haiyang Nuclear Power Plant is a nuclear power plant in Haiyang, Shandong province, China. It is the second site to house AP1000 units, after the Sanmen Nuclear Power Station.
History
Groundbreaking happened one month ahead of schedule on July 30, 2008.[1] Construction of the first unit began in September 2009.[2] Civil construction of Unit 1 was completed 29 March 2013.[3] Fuel loading at Haiyang 1 began on June 22, 2018.[4] First grid connection was on 17 August 2018.[5] Unit 1 began commercial operation on 22 October 2018.[6]
Construction of unit 2 started in June 2010, at that time the fourth Chinese AP1000 project together with the two units of the Sanmen NPP.[7] Commercial operation began in January 2019, after having completed a full-power test run for a week (168 hours). Both units will provide together about 20 TWh of electricity to the grid of Shandong province.[8]
On July 7, 2022, construction began on unit 3 after authorization had been granted.
Reactor data
Unit | Type /Model | Net power |
Gross power |
Thermal power |
Construction start |
First criticality |
Grid connection |
Operation start |
Notes |
---|---|---|---|---|---|---|---|---|---|
Phase I | |||||||||
Haiyang 1 | PWR / AP1000 | 1170 MW | 1250 MW | 3415 MW | 2009-09-24 | 2018-08-08 | 2018-08-17 | 2018-10-22 | [5] |
Haiyang 2 | PWR / AP1000 | 1170 MW | 1250 MW | 3415 MW | 2010-06-20 | 2018-09-29 | 2018-10-13 | 2019-01-09 | [9] |
Phase II [10] | |||||||||
Haiyang 3 | PWR / CAP1000 | 1161 MW | 1253 MW | 3400 MW | 2022-07-07 | [11] | |||
Haiyang 4 | PWR / CAP1000 | 1161 MW | 1253 MW | 3400 MW | 2023-04-22 |
District Heating
In September 2020, the plant's owner and a thermal company instigated a plan to heat all of Haiyang city via heat exchange.[12] Two months later, 700,000 square meters of housing had been heated and the project was en route for completion in its entirety in 2021.[13][14] The switch to clean energy[12] is expected to eliminate more than 180,000 tonnes of fossil fuel emissions each year, and the corresponding reduction in air pollution is anticipated to save about 600 lives annually.[15] By November 2022, the plant used 345 MW-thermal effect to heat 200,000 homes, replacing 12 coal heating plants.[16]
See also
References
Шаблон:Nuclear power in the PRC
- ↑ NucNet. Ground Broken At Site Of China’s Haiyang Nuclear Power Plant Шаблон:Webarchive. July 30, 2008.
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ 5,0 5,1 Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ 12,0 12,1 Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- Английская Википедия
- Nuclear power stations in China
- Power stations in Shandong
- Nuclear power stations using AP1000 reactors
- 2018 establishments in China
- Nuclear power stations with reactors under construction
- Nuclear power stations with proposed reactors
- Haiyang
- Страницы, где используется шаблон "Навигационная таблица/Телепорт"
- Страницы с телепортом
- Википедия
- Статья из Википедии
- Статья из Английской Википедии