Шаблон:Use dmy dates Шаблон:Use Australian English Шаблон:Main Шаблон:Update The National Broadband Network had its origins in 2006 when the Federal Labor Opposition led by Kim Beazley committed the Australian Labor Party, if elected to government to a 'super-fast' national broadband network. Initial attempts to engage key businesses in Australian telecommunications in planning and development; and implementation and operation failed with NBN Co being set up in 2010 to have carriage of the 'largest infrastructure' project in Australia's history.
Completion of the project is anticipated to be in the early 2020s.
2006–2007
Pre-2007 federal election
On 11 August 2005 Sol Trujillo, the newly appointed CEO of Telstra, gave his first presentation, "The Digital Compact & National Broadband Plan: Enabling Regulatory Reform" [1] to both the Howard government and select investors. Australian Securities Exchange continuous disclosure rules forced the presentation to be shared with all investors, published on Telstra & ASX sites. This is one of the earliest uses of "National Broadband Plan", the origin of the $4.7 billion of Government equity to build a 12Mbit/s FTTN NBN, "94% Rural" and "99% Urban". There were two other proposed options, for 6Mbit/s for $2.6B and 1.5Mbit/s for $1.1B. [PDF page 47 of TLS-339, pg 15 of "National Broadband Plan" slides.]
The opposition Labor Party proposed that if elected, it would commence the construction of a 'super fast' national broadband network (NBN). The initial proposal would see fibre to the node (FTTN) technology for 98% of Australian households with a minimum speed of 12 Mbit/s, and the remaining 2% would "have improved broadband services".[2][3][4] The network was initially estimated to cost Шаблон:Nowrap including a government contribution of Шаблон:Nowrap which would be raised in part by selling the Federal Government's remaining shares in Telstra.[5]
The Howard government's $2 billion broadband plan would see regional areas to get WiMAX wireless and ADSL2+ broadband. At no cost to the tax-payers, the private sector would tender to build a FTTN broadband network in built-up areas capable of delivering internet speeds of up to 50 Mbit/s.[6]
2007 Federal election
The Labor Party won the November 2007 federal election, and the Rudd government was sworn into office on 3 December. Soon afterwards, Senator Stephen Conroy announced the newly elected government's commitment to building a national high-speed broadband FTTN network.[7]
2008
Initial Request for Proposal
Request for Proposal (RFP) to build the NBN issued, compliant proposals were received from Acacia, Axia NetMedia, Optus on behalf of Terria, TransACT and the Government of Tasmania (covering their respective states only),[8][9][10][11] a non-compliant proposal was received from Telstra and they were excluded from consideration.[12][13]
There were suggestions that if the project were to go ahead, Telstra's exclusion could lead to them being entitled to compensation estimated at Шаблон:Nowrap.[14][15]
Bidders who lodged compliant proposals were neither able to meet the government's requirements nor able to raise the necessary capital during the global financial crisis, the RFP was terminated on Шаблон:Nowrap.[16]
2009
After terminating its initial RFP, the Rudd Government announced it would bypass the existing copper network by constructing a new national network combining fibre to the premises (FTTP), fixed wireless and satellite technologies.[17] The FTTP rollout was planned to reach approximately 93% of premises in Australia by Шаблон:Nowrap.
For each percentage point of coverage above 93%, FTTP build costs become prohibitive because of a low population density.[18] However, the FTTP footprint could be expanded where users or communities were willing to pay the incremental costs of installing FTTP.[19]
The FTTP rollout was to gradually replace the copper network then owned by Telstra and used for most telephone and data services. As part of an agreement with NBN Co, Telstra was to move its customers to the NBN, and lease space in its telephone exchanges and access to its extensive network ducting.
Tasmania was selected for a trial deployment based on the Tasmanian Government's submission to the RFP.[16]
At the same time, the federal government threatened to force a structural separation of Telstra.[20][21]
Initial expected cost and payback
The Rudd Government estimated to the capital expenditure of the project initially to be Шаблон:Nowrap. NBN Co later revised down the cost in its business plan to Шаблон:Nowrap.[22] The project was to be financed by a combination of a Federal Government investment of Шаблон:Nowrap and private investment for the remainder.[22]
NBN Co intends to begin paying dividends back to the Federal Government in 2021, and to have fully repaid the Government's contribution by 2034.[23] NBN Co's business plan forecasts a return on investment of 7.1%, expecting to turnover revenue of Шаблон:Nowrap by 2021.[24]
NBN Co set up
NBN Co was established on Шаблон:Nowrap.[25][26] Mike Quigley was appointed chief executive officer on Шаблон:Nowrap.[27]
2010
An implementation study was commissioned in Шаблон:Nowrap and released on Шаблон:Nowrap by the Rudd Government.[28] McKinsey & Company and KPMG concluded the NBN can be implemented and made 84 recommendations in the study, including expanding the fibre footprint to 93 per cent from the original 90 per cent.[29]
NBN Co Request for tender (RFT) (April 2010)
In April 2010, NBN Co began a tender for the major FTTP rollout. Fourteen vendors submitted a proposal; however, NBN Co suspended the process on Шаблон:Nowrap, as the prices were 'unacceptably high'.[30]
Abbott and Turnbull rejection of NBN (July–October 2010)
Tony Abbott, as Leader of the Opposition, and Malcolm Turnbull, as Shadow Minister for Communications, indicated in 2010 that they would 'demolish' the NBN.[31][32] They argued that the demand for such a service was not significant,[note 1] and thus the estimated cost was too high and the timeline for implementation too long.
First customers (July 2010)
The first customers connected in Шаблон:Nowrap.[33][34]
2010 election (21 August 2010)
3 days before the election, at the 2010 Charles Todd Memorial Oration[35][36] of the Australian Computer Society, Mike Quigley attacked the Coalition broadband proposals in breach of the Caretaker conventions[37]
2010 Australian federal election with the election of the minority Gillard government led to priority being given to regional and rural areas.[38][39] Also an increase in the peak speed to one gigabit per second was announced[40] in response to Google Fiber[41]
Business plan (20 December 2010)
NBN Co released its business plan on Шаблон:Nowrap, including forecasts and network design.[42]
Changes to the Business plan included an increase in the peak speed to one gigabit per second,[40] in response to Google Fiber[41] and giving 'priority' to regional and rural areas during the rollout following the events after the 2010 election.[38][39] It has been argued that the early sites chosen for the NBN were selected due to political reasons.[43]
Trial rollout in Tasmania (2010)
Tasmania was selected as the first state[44] to begin the rollout of the NBN, based on the Tasmanian Government's 'shovel ready'[45] submission to the RFP for the original NBN.[16] A new company, NBN Tasmania (previously Tasmania NBN Co),[46] was formed on Шаблон:Nowrap to build the NBN in Tasmania.[47] The company was planned to be a joint-venture between NBN Co, Aurora Energy and the Tasmanian Government.[45] The Tasmanian Government also floated an idea to invest Шаблон:Nowrap in Aurora Energy to get access to its fibre network; however, the joint-venture and deal were both cancelled on Шаблон:Nowrap when the negotiations reached an impasse.[45][48] Although the joint-venture was cancelled, Aurora Energy still plays a role in the construction of the NBN in Tasmania.[49]
The trial rollout in Tasmania comprises three stages. Stage one was announced on Шаблон:Nowrap with the first customers being connected a year later.[33][34] Stage one included connections to premises in Smithton, Scottsdale and Midway Point[49] and construction of fibre 'backbones' from Port Latta to Smithton, Cambridge to Midway Point, Midway Point to Triabunna, George Town to Scottsdale and Scottsdale to St Helens.[50] On completion of stage one, 4,000 premises were offered fibre installation; 51 agreed to be 'NBN Ready' (at no cost), but only 10.9% actually took up the service.[51] As of Шаблон:Nowrap, 712 premises had an active service and 11 premises were awaiting service activation by a retail service provider (RSP).[49]
The Tasmanian Parliament passed opt-out legislation on Шаблон:Nowrap,[52] to allow NBN Co to install fibre connections to premises unless the property owners explicitly decline the installation.[53] The fibre connection is free, however, if the installation is declined and a connection is ordered at a later date, NBN Co may charge a connection fee.[54] The bill passed the Tasmanian lower house with the support of all members.[52]
During his second reading speech, Premier of Tasmania David Bartlett said the take-up rates were 'a good early result'; however, he said it was 'important to increase the participation rate'.[54] In his closing remarks, Bartlett said '[the] NBN in Tasmania is a once-in-a-generation opportunity to create jobs and contribute to a new economic direction'.[55] In her second reading speech on behalf of the Tasmanian Opposition, Elise Archer said 'the NBN is an important infrastructure', but that 'the State Liberals have some concern that the NBN business model seems to rely more and more on eliminating competition and other technologies'.[56]
Stages two and three were announced on Шаблон:Nowrap and Шаблон:Nowrap, respectively. Approximately 11,150 premises in Sorell, Deloraine, George Town, St Helens, Triabunna, Kingston Beach and South Hobart were included in stage two.[57][58] Stage three includes approximately 90,000 premises in Hobart, Launceston, Devonport and Burnie.[59] Stage two will include a trial of expanding the FTTP footprint to areas not included in the initial rollout. The trial will allow individuals and councils to pay the incremental cost of a fibre connection over fixed wireless in order to receive a fibre connection from NBN Co. The costs will include provisioning further space in exchanges and rolling out additional fibre optic cables.[60]
At the time of launch, the access prices for RSPs were temporarily set at a flat rate of A$300 per premises with no ongoing monthly charges.[61] Mike Quigley said one of the reasons for the flat rate is the OSS and BSS systems was not built to make the process automatic. He continued if NBN Co charged a monthly charge without the systems, it would have been a 'very manually intensive process' and not a 'sensible proposition'.[62] However, RSPs did charge a monthly fee to customers, to cover the cost of the trial.[62]
Of the first 4000 residences in Hobart, only 10.9% have actually taken up a service.[51] However, as part of the agreement with Telstra is to decommission the existing copper network as the NBN becomes available, this is not considered as representative of the ultimate NBN adoption by customers.[63]
2011
National Broadband Network Companies Act 2011 (28 March 2011)
The Parliament passed the National Broadband Network Companies Act 2011 and a related bill on Шаблон:Nowrap[64] with amendments by the Greens and independent senators adopted on Шаблон:Nowrap.[65] The amendments centred around transparency, freedom of information and competition concerns, including the adoption of uniform national wholesale prices for NBN connections.[66][67] The Government has required support from the Greens to pass NBN legislation through the Parliament. The Greens have voted in favour of NBN legislation, but have also won support for amendments that make NBN Co subject to freedom of information laws,[68] and that make any proposal to privatise the NBN subject to review by the Parliament and by the Productivity Commission.[69]
NBN Co Request for tender of April 2010 terminated (1 April 2011)
Fourteen vendors submitted a proposal; however, NBN Co suspended the process on Шаблон:Nowrap, as the prices were 'unacceptably high'.[30]
Principal contractor agreement with Silcar (1 June 2011)
NBN Co entered into an agreement worth up to Шаблон:Nowrap with Silcar on 1 June 2011. The agreement covered the construction of the NBN in Queensland, New South Wales and the Australian Capital Territory by Silcar, a company joint-owned by Siemens and Thiess.[70] The agreement also includes the option of a two-year extension with an additional value of Шаблон:Nowrap.[71]
Agreement with Telstra (23 June 2011)
NBN Co signed an agreement with Telstra on Шаблон:Nowrap estimated to be worth Шаблон:Nowrap post-tax net present value,[72] building upon the signing of a financial heads of agreement a year beforehand.[73]
Instead of separating wholesale and retail operations, Telstra agreed to 'disconnect'[74] its Internet customers from the copper and hybrid fibre-coaxial networks in areas where FTTP has been installed, and agreed to lease dark fibre, exchange space and ducts to NBN Co. as part of the agreement, Telstra would not be able to market their mobile network as an alternative to the NBN for a number of years.[72]
The agreement with Telstra required that the copper telephone network be decommissioned in an area 18 months after optic fibre is ready for service and that new connections were to be made to the optic fibre network and not the copper network. In some cases, premises have been left without service due to lengthy delays in establishing NBN connections. Telstra advises the use of the mobile network for phone and internet in these cases.[75][76]
Agreement with Optus (23 June 2011)
NBN Co signed an agreement with Optus over its hybrid fibre-coaxial network estimated to be worth Шаблон:Nowrap post-tax net present value.[77] The ACCC—whose approval is required before both agreements take effect—raised concerns about the clauses being anti-competitive.[78]
First release sites (2011)
Five areas comprising around 14,000 premises were chosen as the 'first mainland sites', each representing rollout challenges the NBN was expecting to face during an Australia-wide rollout, with the first services going live on Шаблон:Nowrap.[79][80][81] commenced on Шаблон:Nowrap,[82][83]
- Armidale was the first site to officially launch on Шаблон:Nowrap with 2,900 premises included of which 90% did not opt out for connection.[84][85]
- Kiama Downs and Minnamurra was the second site to officially launch, following Armidale on Шаблон:Nowrap. Approximately 2,350 premises were passed, of which 80 per cent did not opt out for installation.[86]
- Brunswick had the lowest installation rate at the time of its official Шаблон:Nowrap launch: of the approximately 2,689 premises passed, only 50% opted for installation.[87]
- Aitkenvale and Mundingburra followed Brunswick on Шаблон:Nowrap with approximately 3,100 premises passed and 63 per cent did not opt out for installation.[88]
- Willunga was the fifth and final 'first release site' to officially launch on Шаблон:Nowrap with approximately 940 premises passed and 91 per cent did not opt out for installation.[89]
These figures are for passive installation of a dark fibre to the premises. To activate it residence need to purchase a service from an RSP.[89]
Furthermore, following the low take up rates in Tasmania, the government has adopted an opt-out model in which users are assumed to want the service unless they explicitly opt-out.[90]
Thus passive installation figures may be quite different from the proportion of residences that actually use the NBN service.
Second release sites
Fourteen second release sites comprising 54,000 premises in all states and territories were announced on Шаблон:Nowrap with construction commencing in Шаблон:Nowrap.[91]
The sites comprise premises in Aspley, Bacchus Marsh, Casuarina, Coffs Harbour, Geraldton, Gungahlin, Mandurah, Modbury, Prospect, Riverstone, South Morang, Springfield Lakes, Toowoomba and Victoria Park.[92][93]
Telstra had agreed to allow NBN Co to use its exchanges and ducts in the second release sites before the agreement was finalised.
2012
The opposition Liberal/National Coalition's Malcolm Turnbull addressed significant attacks on the NBN, these focused on the estimated cost and timeline for implementation and the build cost, with specific attacks on the expense of the Long Term Satellite Service.[94]
- 'Don't buy yourself a Camry, a Falcon - buy yourself a Rolls-Royce, a Bentley,' opposition communications spokesman Malcolm Turnbull told reporters in Canberra today.
- 'Nothing but the best will do, nothing but the most expensive will do.'
- Mr Turnbull said the industry had told him there was enough capacity on existing and scheduled-to-be-launched satellites to provide broadband services to rural and remote Australia. As well, the existing interim satellite service could be upgraded to a permanent one.
- 'Why does the government have to pay over $1 billion in total in building, launching, flying these satellites of their own?' Mr Turnbull said.
Later they commented that in government they would take an 'agnostic' approach.[95]
2013
The MTM was selected as the approach to broadband provision by the Liberal–National coalition in the lead up to the 2013 Australian federal election.[96][97]
2013 Federal election (7 September 2013)
After the 2013 election, the Abbott government, with Malcolm Turnbull as Minister for Communications,[98] the new communications minister Malcolm Turnbull announced immediate changes to the government's NBN plans:[99][100] much of the NBN Board was asked to resign;[101] Ziggy Switkowski was appointed new chairman.[102] Turnbull announced that the FTTP rollout would continue in the short term, with the probability that rollout will be downgraded to 'alternative technologies' such as Fibre to the node after a 60-day review was completed.[103]
A number of studies and a strategic review into the NBN were commissioned. The strategic review was to determine the ideal infrastructure mix to deliver fast broadband across the country as quickly as possible and reduce establishment costs.[104][105]
On 12 December 2013, the NBN Board appointed Bill Morrow as NBNCo's new CEO, replacing Mike Quigley.[106] Quigley had announced his intention to resign from NBNCo in July 2013.[107] Morrow resigned from his role as CEO of Vodafone Australia to accept the appointment with NBNCo.
Telstra responded to the prospect of changes by asserting its intention to retain the $11bn value it generates from the previous government's deal.[108]
The NBN faced delays due to a lack of skilled fibre splicers in Australia and some work had to be re-done due to the inadequate training given to many of the workers.[109]
Delays and health concerns occurred in 2013 when work was stopped for several weeks at a number of sites after asbestos was found in Telstra pits.[110][111]
After the 2013 election, the former communications minister Stephen Conroy conceded that the initial rollout plans were 'too ambitious' and that there were delays in implementation.[112]
Multi-Technology Mix (MTM)
Malcolm Turnbull announced in 2013 that the NBN would be delivered using a mix of old and new technology, a Multi-Technology Mix, stating that it would allow significant savings on the earlier Fibre to the Premises and earlier completion to the approach chosen by the Gillard and Rudd governments.[113][114] The MTM has been the focus of criticism regarding cost overruns and the delay in delivering the NBN.[115][116]
The MTM includes:
- Fibre to the Curb (FTTC) - previously Fibre to the distribution point (FTTdp), replacing Optus HFC.
- Fibre to the node (FTTN) - The technology to provide most NBN connections, replaces FTTP as the preferred technology.
- Hybrid fibre-coaxial (HFC) - was to be shut down, but now the Telstra HFC network is being maintained, while the Optus network is to be upgraded to FTTC.
Progress 2013
At 3 November 2013, construction of the network had passed 354,793 premises and there were 109,862 active customer services.[117] In areas where the FTTP network is being rolled out, a similar agreement with Optus is in place.
2014
In April 2014, The Australian newspaper judged the NBN rollout in Tasmania, its first location, as 'shambolic' and 'abysmal'.[118]
The MTM approach finalised with the Abbott government promising significant savings on the earlier Fibre To The Premises and earlier completion to the approach chosen by the Gillard and Rudd governments.[113][119]
Initial costs and timing for the Coalition NBN were Шаблон:Nowrap of public funding to construct by 2019.[96]
In December a new agreement was finalised with Telstra and Optus for purchase of copper and HFC networks, for a similar cost to the existing compensation for shutting down those networks. Telstra accepted $11B for its part of the network, less a discount for a “remediation credit” where parts of the network required maintenance.[120]
Black spot policy (February 2014)
In February 2014 the government produced the MyBroadband[121] website to provide information about access to the internet. It showed that there were 1.6 million premises across Australia with either no access to fixed broadband or very poor broadband connectivity.[122]
The Minister Malcolm Turnbull stated that the black spots would be a higher priority,[123] without however directing NBN Co address them.[124] There is concern that the NBN will continue to focus on areas that already have relatively fast copper broadband, and thus avoid addressing people that have no or very limited broadband for the foreseeable future.[123][125] In May 2014 then NBN announced that it would be targeting premises that were already serviced with fibre by rival TPG.[126]
2015
In 2015, Quigley criticised cost blowouts in the NBN, saying they were the fault of changes made to the rollout plan introduced by the Coalition government.[127][128][129][130]
Sky Muster I (NBN-Co 1A) was launched on 1 October 2015[131] from the Guiana Space Centre in French Guiana, South America, alongside Argentina's ARSAT-2, on an Ariane 5ECA rocket.
Progress 2015
At 30 June 2015, the company announced 1,011,973 premises are now able to order NBN services. Of that, 571,527 brownfields and 180,796 greenfields premises are able to order fixed-line services, Communications Minister Malcolm Turnbull said. An additional 220,917 premises are able to order services in fixed wireless, and 38,743 premises have connected to the interim satellite service.[132] There were 485,615 active users.[133]
2016
With Malcolm Turnbull becoming Prime Minister of Australia, Mitch Fifield became the Minister for the communications portfolio, and thus the NBN.
Substantial cost over-runs and delays in the delivery of the MTM have subsequently been reported.[116][134][135]
Sky Muster I (NBN-Co 1A) became operational in April 2016.[136]
Sky Muster II (NBN-Co 1B) was launched on 5 October 2016.[137]
Progress 2016
At 30 June 2016, the company had passed 2,893,474 premises across all technologies.[138] Company annual revenue was $421 million compared to $164 million in 2015 financial year, with approximately 1,100,000 active user at June 30.[133]
2017
A September 2017 report by the Joint Standing Committee on the National Broadband Network found significant issues with the technology used by the NBN and the performance of NBN Co, all but one of the Coalition members of the committee released a dissenting report strongly defending the NBN and NBN Co.[139][140][141]
In response to the imminent broadcast of a documentary critical of the performance of the NBN on Four Corners, Malcolm Turnbull stated that the NBN was a failure, blaming the earlier Rudd and Gillard governments.[142][143] The Four Corners documentary noted significant issues with the roll out and complaints regarding performance of the NBN.[144] Following the Prime Minister's acknowledgment of the NBN's failure, Kevin Rudd noted that, on assuming government in 2013, Malcolm Turnbull, as Minister for Communications in the Abbott government radically changed the technical aspects of the NBN.[145]
2019
NBN Co's chief executive Stephen Rue announced in August 2019 that the $51 billion project would be completed within budget by June 2020.
Progress
At the time of the announcement, the network was 85% complete.[146]
2020
In February 2020, Rue announced that the network was 90% complete. He also reaffirmed his August 2019 announcement that the project would be completed within budget by June 2020.[147]
National rollout
NBN Co planned to complete the FTTP rollout by Шаблон:Nowrap,[148] along with the completion of the fixed wireless[149] and satellite rollout by 2015.[150][151]
NBN Co initially planned to complete the MTM rollout by 2020.
References
- Notes
- Sources
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite press release
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite press release
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ 16,0 16,1 16,2 Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ 22,0 22,1 Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Cite magazine
- ↑ Шаблон:Citation
- ↑ 30,0 30,1 Шаблон:Citation
- ↑ Emma Rodgers, (14 September 2010), Abbott orders Turnbull to demolish NBN, ABC News. Retrieved 12 February 2017
- ↑ AAP, (14 September 2010), Turnbull back to 'demolish' NBN, Sydney Morning Herald. Retrieved 29 July 2010
- ↑ 33,0 33,1 Шаблон:Citation
- ↑ 34,0 34,1 Шаблон:Citation
- ↑ Mike Quigley, CEO NBN Co, (18 August 2010), 2010 Charles Todd Memorial Oration, Australian Computer Society
- ↑ Mike Quigley, CEO NBN Co, (18 August 2010), 2010 Charles Todd Memorial Oration presentation slides, NBN Co
- ↑ Renai LeMay, (18 August 2010), Quigley openly slams Coalition’s broadband policy, Delimiter
- ↑ 38,0 38,1 Шаблон:Citation
- ↑ 39,0 39,1 Шаблон:Citation
- ↑ 40,0 40,1 Шаблон:Citation
- ↑ 41,0 41,1 Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Cite journal
- ↑ Шаблон:Citation
- ↑ 45,0 45,1 45,2 Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ 49,0 49,1 49,2 Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ 51,0 51,1 Шаблон:Citation
- ↑ 52,0 52,1 Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ 54,0 54,1 Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ 62,0 62,1 Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ 72,0 72,1 Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ 89,0 89,1 Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ [http://www.news.com.au/breaking-news/turnbull-says-nbn-satellites-a-rolls-royce-option/news-story/50e71eeee14748919f1750ef6a86e741 Turnbull says NBN satellites a Rolls-Royce' option news,com.au 8 February 2012
- ↑ IT Pro, (29 June 2012), We will not cancel the NBN: Turnbull, Sydney Morning Herald. Retrieved 29 July 2017
- ↑ 96,0 96,1 Шаблон:Cite news
- ↑ Caitlin Fitzsimmons, (9 Apr 2013 updated 10 Apr 2013), Abbott, Turnbull detail Coalition’s 25Mbps broadband plan, AFR Weekend Retrieved 12 February 2017
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ All but one NBN Co board member hand in resignations - ABC News (Australian Broadcasting Corporation). Abc.net.au (2013-09-23). Retrieved on 2013-10-29.
- ↑ Ziggy Switkowski confirmed as chairman of NBN Co by Communications Minister Malcolm Turnbull - ABC News (Australian Broadcasting Corporation). Abc.net.au (2013-10-03). Retrieved on 2013-10-29.
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Reports and audit into the NBN commissioned by the Abbott government in 2013
- (20 February 2014), Broadband Availability and Quality Report
- Bill Scales, (7 March 2014), Independent audit of the NBN public policy process looking at the public policy processes that led to the establishment of the NBN in the period April 2008 – May 2010, Media Release: Independent audit of the NBN public policy process, (7 March 2014), Department of Communications and the Arts Retrieved 10 March 2016
- Independent cost‐benefit analysis of broadband and review of regulation
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ The NBN will survive the federal election - The Drum (Australian Broadcasting Corporation)
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ NBN rollout was too ambitious: Stephen Conroy. Brisbanetimes.com.au (2013-10-11). Retrieved on 2013-10-29.
- ↑ 113,0 113,1 Ben Grubb, (9 April 2014), Malcolm Turnbull locks in multi-technology NBN, The Sydney Morning Herald Retrieved 10 March 2016
- ↑ (1 November 2015), Turnbull's faster, cheaper NBN, Background Briefing, Radio National, Retrieved 10 March 2016
- ↑ Mike Quigley, (September, 2015)Exploding Malcolm Turnbull’s Myths, ABC Retrieved 10 March 2013
- ↑ 116,0 116,1 Paul Budde, (2 March 2016), Has Malcolm Turnbull lost his opportunity for change?, ITWire Retrieved 10 March 2016
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ (1 November 2015), Turnbull's faster, cheaper NBN, Background Briefing, ABC Radio National, Retrieved 10 March 2016
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite webШаблон:Cbignore
- ↑ Byron Connolly, (20 February 2014), New website identifies NBN blackspots, CIO
- ↑ 123,0 123,1 Simon Sharwood, (9 Apr 2014), Turnbull leaves Australia's broadband blackspots in the dark, The Register
- ↑ Simon Sharwood, (14 April 2014), Turnbull gave NBN Co NO RULES to plan blackspot upgrades, The Register
- ↑ Шаблон:Cite web
- ↑ Richard Chirgwin, (5 May 2014), NBN Co puts October date on first FTTB connections, The Register
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite webШаблон:Dead link
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ 133,0 133,1 Allie Coyne, (16 Aug 2016), NBN passes one million active users on the network, iTnews Retrieved 16 August 2016
- ↑ Renai LeMay, (5 November 2015), Quigley releases detailed evidence showing MTM NBN cost blowout, Delimiter Retrieved 11 March 2013
- ↑ Mike Quigley, (September, 2015) Exploding Malcolm Turnbull’s Myths, ABC Retrieved 10 March 2013
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Joint Standing Committee on the National Broadband Network, (29 September 2017), First report of the 45th Parliament: The rollout of the National Broadband Network, Шаблон:ISBN. Retrieved 29 September 2017
- ↑ Ry Crozier, (29 September 2017), NBN inquiry demands drastic refocus of broadband project: But government unlikely to agree, itnews. Retrieved 29 September 2017
- ↑ Amy Remeikis, (2 October 2017), Nationals MP Andrew Broad bemoans rollout of 'faceless' NBN, The Guardian. Retrieved 3 October 2017
- ↑ Jesse Dorsett, (24 October 2017), NBN Co is a 'calamitous train wreck' that may never make a profit, Malcolm Turnbull says, laying blame with Labor, ABC News. Retrieved 27 October 2017
- ↑ Trevor Marshallsea How Australia's A$49bn internet network came to be ridiculed, BBC. Retrieved 27 October 2017
- ↑ Geoff Thompson and presented by Sarah Ferguson, (23 Oct 2017), What's wrong with the NBN?, Four Corners. Retrieved 27 October 2017
- ↑ Campbell Simpson, (24 October 2017), 'You Changed Horse In Mid-Stream': Kevin Rudd On Turnbull's NBN, Lifehacker. Retrieved 27 October 2017
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
- ↑ Шаблон:Citation
Ошибка цитирования Для существующих тегов <ref>
группы «note» не найдено соответствующего тега <references group="note"/>
- Английская Википедия
- Страницы с неработающими файловыми ссылками
- National Broadband Network
- Infrastructure in Australia
- Rudd government
- Abbott government
- Turnbull government
- Economic history of Australia
- History of telecommunications
- Страницы, где используется шаблон "Навигационная таблица/Телепорт"
- Страницы с телепортом
- Википедия
- Статья из Википедии
- Статья из Английской Википедии
- Страницы с ошибками в примечаниях