The Hyderabad Metro is a rapid transit system, serving the city of Hyderabad, Telangana, India.[1][2][3][4] It is the third longest operational metro network in India after Delhi Metro and Namma Metro (Bengaluru),[3][4] and the lines are arranged in a secant model. It is funded by a public–private partnership (PPP),[5][6] with the state government holding a minority equity stake.[7] Hyderabad Metro is the world's largest elevated Metro Rail system based on DBFOT basis (Design, Build, Finance, Operate and Transfer).[8] A special purpose vehicle company, L&T Metro Rail Hyderabad Ltd (L&TMRHL), was established by the construction company L&T[9][10] to develop the Hyderabad metro rail project.[11][12]
A Шаблон:Convert stretch from Miyapur to Nagole, with 24 stations, was inaugurated on 28 November 2017 by Prime Minister Narendra Modi.[13][14] This was the longest rapid transit metro line opened in one go in India.[15][16] It is estimated to cost Шаблон:INRConvert. As of February 2020, about 490,000 people use the Metro per day.[17] Trains are crowded during the morning and evening rush hours.[18] A ladies only coach was introduced on all the trains from 7 May 2018.[19] Post-COVID, 450,000 passengers were travelling on Hyderabad Metro daily on average by December 2022.[20] On 3 July 2023, Hyderabad Metro Rail achieved ridership clocking in at 0.51 million on that day.[21]
History
Metro Rail Project was approved by Union government, in 2003.[23] As Hyderabad continued to grow, the Multi-Modal Transport System (MMTS) had insufficient capacity for public transport, and the Union Ministry of Urban Development approved construction of the Hyderabad Metro Rail Project, directing the Delhi Metro Rail Corporation to conduct a survey of the proposed lines and to submit a Detailed Project Report (DPR).[24] To meet rising public transport needs and mitigate growing road traffic in the twin cities of Hyderabad and Secunderabad, the state government and the South Central Railway jointly launched the MMTS in August 2005.[25][26] The initial plan was for the Metro to connect with the existing MMTS to provide commuters with alternate modes of transport. Simultaneously, the proposals for taking up the construction of MMTS Phase II were also taken forward.[27]
In 2007, N. V. S. Reddy was appointed Managing Director of Hyderabad Metro Rail Limited,[28] and the same year, Central Government approved financial assistance of Шаблон:INR 1639 crore under a Viability Gap Funding (VGF) scheme.[29] The option of an underground metro system in Hyderabad was ruled out by L&T due to the presence of hard rocks, boulders and the topography of the soil in Hyderabad.[30] Hyderabad Metro initially began under the Andhra Pradesh Municipal Tramways (Construction, Operation and Maintenance) Act, 2008[31] and later on, it came under the Central Metro Act which permitted revision of fares.[32] On 26 March 2018, the Government of Telangana announced that it would set up an SPV "Hyderabad Airport Metro Limited (HAML)", jointly promoted by HMRL and HMDA, to extend the Blue line from Raidurg to Rajiv Gandhi International Airport, Shamshabad, under Phase II after the completion of Phase I in 2020.
Initial bidding
The bidding process was completed by July 2008 and awarded to Maytas,[33] which failed to achieve financial closure for the project as per schedule by March 2009.
Re-bidding
The State government cancelled the contract and called for a fresh rebidding for the project. In the July 2010 rebidding process, Larsen & Toubro (L&T) emerged as the lowest bidder for the Шаблон:INRConvert project.[34] L&T came forward to take up the work for about Шаблон:INRConvert as viability gap funding as against the sanctioned Шаблон:INRConvert. The Nallari Kiran Kumar Reddy government proactively pursued the project, but it was delayed due to separate state agitation and later due to the apprehensions of the new government. A consortium of 10 banks led by State Bank of India sanctioned the entire debt requirement of Hyderabad Metro project, which was the largest fund tie-up in India for a non-power infrastructure Public-private partnership (PPP) project at that time.[35]
Mascot
The mascot of Hyderabad Metro Rail is Niz. It was derived from the word Nizam, who ruled the princely state of Hyderabad.[36]
Construction milestones
- Hyderabad Metro Map, Timings, Route & Fare: Everything You Need To Know [1]
- Groundbreaking (Bhoomi Puja) for the project was conducted on 26 April 2012[37] the concessionaire started the pillar erection on the same day for Stage-I and on 6 June 2012 for Stage-II.[38] The work for Corridor 2 has been delayed due to traders in Koti and Sultan Bazar demanding realignment of the route to safeguard traders and old age heritage markets.[39] If the recent bill proposed in Parliament which allows construction within a Шаблон:Convert radius of heritage structures and sites of historical or archaeological importance is passed, Metro might receive a chance as it helps to connect the Old city with IT corridor.[40]
- The construction of the entire Шаблон:Cvt has been split into 6 stages with the first stage originally scheduled to be completed by March 2015[41][42]
- In November 2013, L&T Hyderabad Metro started laying of rails on the metro viaduct between Nagole and Mettuguda, a stretch of .[43]
- The first highly sophisticated train of the Hyderabad Metro Rail (HMR) came from Korea during the third week of May 2014. Stringent trial runs commenced from June 2014 till February 2015.[44] The trial runs started on the Miyapur to Sanjeeva Reddy Nagar stretch in October 2015.
- CMRS inspection for Stage-II (Miyapur and S.R.Nagar Section) was done on 9, 10 August 2016.[45]
- The steel bridge of the HMR was successfully placed over the Oliphant bridge in August 2017.[46][47]
- In November 2017, Commissioner of Railway Safety (CMRS) granted safety approval for Шаблон:Cvt stretch from Miyapur to SR Nagar, Шаблон:Cvt stretch from SR Nagar to Mettuguda and Шаблон:Cvt stretch from Nagole to Mettuguda.[48]
- 16-km Ameerpet - LB Nagar Metro stretch was opened for commercial operations from 24 September 2018.[49]
- The Ameerpet - HITEC City route was opened on conditional basis on 20 March 2019. The reversal facility after HITEC City metro station was started on 20 August 2019.[50]
- On 19 May 2019, the construction of all the 2,599 pillars for the Шаблон:Cvt Hyderabad Metro rail (except the Шаблон:Cvt stretch in old city) was completed.[51][52]
- The Green Line Corridor from Jubilee Bus Station to Mahatma Gandhi Bus Station was issued the Safety Certificate by the Commissioner of Metro Rail Safety and inauguration of services on the section was done on 7 February 2020 by the Chief Minister of Telangana, K. Chandrashekar Rao.
- Groundbreaking ceremony for Airport Express line was done by Chief Minister of Telangana, K. Chandrashekar Rao on 9 December 2022
Construction phases
Phase I
Phase I of the project includes 3 lines covering a distance of around Шаблон:Convert. The metro rail line between Nagole and Secunderabad was originally scheduled open by December 2015; it was partly opened on 29 November 2017 and the entire Шаблон:Cvt phase 1 completed in 2020.[53]
A 'Supplemental Concession Agreement' was signed between L&T Metro Rail Hyderabad and Government of Telangana, under which L&T Metro Rail Hyderabad was granted an interest free soft loan of Rs 100 crore.[54]
- Line 1 - Red Line - LB Nagar-Miyapur - Шаблон:Cvt 27 stations
- Line 2 - Green Line - JBS–Falaknuma Шаблон:Cvt 15 stations
- Line 3 - Blue Line - Nagole–Raidurg - Шаблон:Cvt 24 stations
Note: Stage 4/2 MGBS–Falaknuma section (Шаблон:Cvt) is also part of the initial phase I, but has been rumored that the state government might take up this section instead of L&T, but will be completed along with the phase I work. The Stage 3/2 HITEC City–Raidurg section (Шаблон:Cvt) of Corridor III was not initial part of phase I, it was later on added by the newly elected state government. This section is opened on 29 November 2019.
Old city metro line
Earlier in 2010, All India Majlis-e-Ittehadul Muslimeen suggested an alternate route for metro in the old city through Purana pul, Muslimjung, Bahadurpura, Zoo Park, Tadbun junction, Kalapathar, Misrigunj and Shamsheergunj to Falaknuma.[55][56][57] However, this Шаблон:Convert route was not accepted. The eastern parts of the old city have access to the metro via the Malakpet metro station.[58] A Шаблон:Convert-long green line in the old city will pass through Dar-ul-Shifa, Salar Jung Museum, Charminar, Shah-Ali-Banda , Shamsheer Gunj , Jungametta and ends at Falaknuma.[59][60] In June 2022, Hyderabad Metro Rail started a fresh survey of the Old City route from MGBS for underground utilities.[61] The survey is through the Lidar, Global Positioning System and Inertial measurement unit and the plan is to build the elevated line alongside Musi river and center of the road. In July 2023, Telangana Chief minister K. Chandrashekar Rao instructed the municipal administration and L&T Chairman to take forward the metro project in old city.[62][63] On 16 July 2023, Hyderabad Metro MD NVS Reddy informed that preparatory works for taking up Metro Rail works in old city has started and land acquisition notices for 1,100 affected properties will be issued in about a month.[64][65] All the five metro stations in the old city will have 120-feet wide roads under the viaduct.[66][67] On 27 August 2023, Hyderabad Metro Rail Limited started a drone survey of the proposed rail alignment in the old city.[68][69][70][71]
Phase II
The Government of Telangana is planning second phase of metro rail covering 67.5 km, to cost Шаблон:INR 17,150 crore.[72][73] The construction of Phase II will be taken up solely by the state government, instead of public–private partnership (PPP) mode in Phase I.[74] Delhi Metro Rail Corporation (DMRC) was entrusted to give a detailed project report (DPR) for Phase II.[75][76] Metro Rail Phase II expansion plan is for about Шаблон:Cvt,[77][78] which includes providing link to Shamshabad RGI Airport.[79] In February 2020, Hyderabad Metro MD NVS Reddy said that three corridors are considered for phase 2. The DPR has been submitted to state government.[80][81]
In November 2022, Telangana government asked the Central Government to sanction the metro rail Phase-II, to be jointly owned by Telangana and the Centre (on the lines of MMTS) with external financial assistance.[82] Telangana government proposed metro rail connectivity for about 26 km from BHEL to Lakdikapul with 23 stations and extension of other stretch from Nagole to LB Nagar covering a distance of about 5 kms with 4 stations.[83] BHEL-Lakdikapul metro rail corridor is expected to pass through Miyapur, Raidurg, Khajaguda Junction, Mehdipatnam, Tolichowki and Masab tank areas. Telangana Government has asked Central Government to sanction Шаблон:INRConvert for metro works in the upcoming union budget for 2023-24.[84] For implementing the project, detailed project reports (DPRs) have already been prepared by the state government with the help of Delhi Metro Rail Corporation (DMRC). The reports have been sent to the Centre. Also the Hyderabad airport metro limited and HMDA will build an elevated Hyderabad Bus Rapid Transit System between Kokapet neopolis and KPHB Colony metro station covering Шаблон:Cvt [85] In March 2023, K. T. Rama Rao said that metro line from Nagole will be extended to LB Nagar, which will further be extended till Hayathnagar. LB Nagar will be extended to Rajiv Gandhi International Airport, Shamshabad.[86] Union government pointed out to certain shortfalls in the Government of Telangana’s plan to build BHEL-Lakdikapul and Nagole to LB Nagar metro route.[87][88][89] K. T. Rama Rao replied in a letter to Union Minister of Housing and Urban Affairs Hardeep Singh Puri that the rejection is discrimination against Telangana.[90][91][92]
Hyderabad Airport Express Metro
Шаблон:Main On 26 March 2018, a special purpose vehicle company, Hyderabad Airport Metro Limited (HAML), was established by Government of Telangana to develop the Hyderabad Airport Metro Express.[93][94]
The Шаблон:Cvt Airport Express Metro Corridor is proposed to have 27-km elevated, Шаблон:Cvt on ground and a Шаблон:Cvt-km underground section to connect to the airport terminal.[95] The airport route will have 9 elevated stations and one underground station.[96] From Raidurg Metro terminal station, it will pass through Khajaguda Junction, touching Outer Ring Road at Nanakramguda junction, traverse along ORR to Shamshabad Airport through the existing dedicated Metro Rail Right-of-Way.[97][98] Chief Minister of Telangana K. Chandrashekar Rao laid the foundation stone for Hyderabad Metro Airport Express on 9 December 2022.[99] It will be built at an approximate cost of Шаблон:INRConvert.[100]
Phase III
In February 2023, K. T. Rama Rao said that BRS government would consider extending the Metro Rail up to Ramoji Film City and other parts of Hyderabad under Phase III, after coming to power for the third consecutive time in the Assembly elections in December 2023.[101][102] In June 2023, Chief Minister of Telangana K. Chandrashekar Rao announced that Hyderabad Metro will be extended further from Rajiv Gandhi International Airport in Shamshabad to Kandukur in Maheshwaram Assembly constituency.[103] He also said that there was a need to extend Hyderabad Metro rail from Patancheru Industrial Area in Sangareddy district to Hayathnagar in Rangareddy district.[104][105][106] In June 2023, K. T. Rama Rao said that BRS government has an ambitious plan to expand the metro network in Hyderabad to 250 km, which will include metro network from Jubilee Bus Station to ECIL.[107]
On 31 July 2023, referring to the expansion of the Hyderabad metro rail, K. T. Rama Rao listed out the proposals cleared by the Cabinet.[108] He mentioned that Government of Telangana has proposed a metro corridor of approximately 415 km in length for city of Hyderabad and its peripheral areas, including 156 km of metro network along the Outer Ring Road.[109]
Metro Rail project Phase-IlI expansion - 6 Metro Extension Corridors, Metro rail all along ORR for its entire length.[110][111] On 18 August 2023, Hyderabad Airport Metro Rail (HAML) invited tenders for the selection of consultants for preparing Preliminary Project Reports (PPRs) and Detailed Project Reports (DPRs) for Phase-III metro rail expansion for 12 corridors of 278 km.[112] The selected consultants have to first submit Preliminary Project Reports within two months and carry out traffic surveys, ridership estimates.
Government of India will be requested to provide necessary clearance through the MoD area. In September 2023, Aarvee Associates and SYSTRA bagged two package contracts each for preparing the Detailed Project Reports (DPRs) for the proposed third phase of Hyderabad Metro Rail (HMR) project.[113][114]
Phase-III Part A
- Warangal Highway: Uppal-Ghatkesar-Bibinagar Corridor (25 km; Rs.6,900 Cr)- E 90° degree from Hyderabad Central.
- Vijayawada Highway: L.B.Nagar-Hayatnagar- Peddamberpet Corridor (13 km; Rs.4,500Cr)- SE 120°
- Kurnool Highway: Shamshabad in Metro station-Kothur-Shadnagar Corridor (28 km; Rs.6,800 Cr).SW 210°
- Pune Highway: BHEL-Patancheru-Isnapur Corridor (13 km; Rs.3,250 Cr)- NW 315°
- Srisailam Highway* : Shamshabad Airport-Tukkuguda ORR-Maheswaram X road-Kandukur Corridor (26 km; Rs.6,600 Cr)-S 180°
- Keesara Highway* : Tarnaka - ECIL Elevated Metro (8 Km; Rs.2300 Cr).NE 70°
Phase-III Part B
ORR Metro Corridors: The entire stretch of ORR will have metro network. The ORR features two double-elevated stretches along with the metro.[115]
Phase-III Part C
Elevated 2-Level Corridors: An elevated two-level corridor (one that will be exclusively for metro rail) at the following routes with a flyover and a metro line on top of it.
- Karimnagar Highway: Secbad JBS to Tumkunta - NE 45°(Not Possible due to army quarters)
- Nizamabad Highway: Paradise junction to Kandlakoya via Kompally - NE 30°
Current phases
The construction work was undertaken in two phases. There are six stages of completion in Phase I.[116]
Phase 1 Network | ||||||
---|---|---|---|---|---|---|
No. | Line Name | Terminals | Distance | Line | Opening Date | |
1 | rowspan="2" style="background:#Шаблон:Rcr; text-align: center;" | Red | Miyapur | Ameerpet | Шаблон:Cvt | Line I | 29 November 2017 |
Ameerpet | LB Nagar | Шаблон:Cvt | 24 September 2018 | |||
2 | style="background:#Шаблон:Rcr; text-align: center;" | Green | JBS | MGBS | Шаблон:Cvt | Line II | 7 February 2020 |
3 | rowspan="3" style="background:#Шаблон:Rcr; text-align: center;" | Blue | Ameerpet | Nagole | Шаблон:Cvt | Line III | 29 November 2017 |
Hitech City | Ameerpet | Шаблон:Cvt | 20 March 2019 | |||
Raidurg | Hitech City | Шаблон:Cvt | 29 November 2019 | |||
Phase 2 Network | ||||||
No. | Line Name | Terminals | Distance | Line | Opening Date | |
1 | style="background:#Шаблон:Rcr; text-align: center;" | Blue | Raidurg | American Consulate | Шаблон:Cvt | Line II extension | Proposed[117][118] |
2 | rowspan="2" style="background:#Шаблон:Rcr; text-align: center;" | Red | Miyapur | Patancheruvu | Шаблон:Cvt | Line I extension | |
3 | LB Nagar | Hayathnagar | Шаблон:Cvt | Line I extension | ||
4 | rowspan="2" style="background:#Шаблон:Rcr; text-align: center;" | Green | MGBS | Falaknuma | Шаблон:Cvt | Line II | Yet to start construction |
5 | Falaknuma | Chandrayangutta | Шаблон:Cvt | Line III extension | Proposed[117][118] | |
6 | TBA | Nagole | RGIA | Шаблон:Cvt | TBA | |
7 | Mallardevpally | Rajendranagar | Шаблон:Cvt |
Network
Шаблон:Main Currently, the Hyderabad Metro has 57 stations. Phase I of the Hyderabad metro has 64 stations; they have escalators and elevators to reach the stations, announcement boards and electronic display systems. The stations also have service roads underneath them to for other public transportation systems to drop-off and pick-up passengers.[119] The signboards of Hyderabad Metro are displayed in Telugu, English, Hindi and Urdu at metro stations.[120] All stations of Hyderabad Metro Rail are equipped with tactile pathway right from street level till the platform level along with elevator buttons equipped with Braille, for providing a barrier less navigation for the visually impaired commuters.
Otis Elevator Company supplied and maintains the 670 elevators in use on the system.[121] The numbering of metro pillars of Hyderabad Metro is alpha-numeric with corridor I (Miyapur-LB Nagar) designated as ‘A’, corridor II (JBS-Falaknuma) designated as ‘B’ and corridor III (Nagole-Raidurg) designated as ‘C’.[122][123] The numbering begins from the Point of Beginning (POB) corridor-wise like the pier numbers on corridor I is C1 near Nagole bridge (corridor beginning), C296 near Mettuguda, C583 near Begumpet, C623 near Ameerpet, C1001 near Hitec city, and C1052 near Riadurg. Any future expansion of corridors would be having D, E, F etc. The metro Rail pillars are linked them with Google Maps and GPS (Global Position System).[124]
In May 2018, L&T Metro Rail signed a contract with Powergrid Corporation of India to install electric vehicle charging facilities at all metro stations beginning with Miyapur and Dr. B R Ambedkar Balanagar stations.[125][126] L&THMRL has set up free wifi access units for commuters at Miyapur, Ameerpet and Nagole metro stations, in association with ACT Fibernet, as part of a pilot project.[127][128] Metro Rail Phase II expansion plan is for about Шаблон:Cvt.[129] In April 2019, K. T. Rama Rao said that Шаблон:Convert of metro rail was planned for Hyderabad, with metro along entire Outer Ring Road.[130] All metro corridors are scheduled to terminate at Shamshabad, near Rajiv Gandhi International Airport, as planned in Hyderabad Metro Rail Phase-II.[131] In August 2019, KT Rama Rao said that state cabinet has approved the Hyderabad Metro Airport Express Link from Raidurg to the airport.[132]
Current status
Line | First operational | Last extension | Stations | Length | Terminals | Average Frequency (Minutes) | |
---|---|---|---|---|---|---|---|
style="background:#Шаблон:Rcr; text-align: center;" | Red | 29 November 2017 | 24 September 2018 | 27 | Шаблон:Cvt | Miyapur | LB Nagar | 4.5 minutes (Peak Hours)
7 minutes (Non-Peak hours) |
style="background:#Шаблон:Rcr; text-align: center;" | Blue | 29 November 2019 | 23 | Шаблон:Cvt | Raidurg | Nagole | ||
style="background:#Шаблон:Rcr; text-align: center;" | Green | 7 February 2020 | Yet to start construction | 9 | Шаблон:Cvt | JBS PG | MGBS | |
59 | Шаблон:Cvt |
Lines
Since the first version of the plans, the three corridors mostly remained the same, but minor changes were introduced. These include the lack of stop at Lalaguda, or a stop at Lakdikapul instead of Secretariat. Also, the lines have been marked with several different combination of color.[133] Ameerpet- LB Nagar metro stretch opened on 24 September 2018.[134] HiTec City to Raidurg, Шаблон:Convert stretch on Corridor Three - Nagole to Raidurg, is opened on 29 November 2019,[135][136] as it involves construction of 49 pillars and the Raidurg terminal station.[137]
Red Line: Miyapur–L.B. Nagar
Шаблон:Main
Route length – Шаблон:Cvt
Number of stations (All elevated) – 27
Link to other corridors
- At Ameerpet – connecting corridors 1 and 3
- At Mahatma Gandhi Bus Station – connecting corridors 1 and 2
# | Station Name | Opened | Connections | Alignment |
---|---|---|---|---|
1 | Miyapur | 29 November 2017 | None | Elevated |
2 | J.N.T.U College | 29 November 2017 | None | Elevated |
3 | K.P.H.B. Colony | 29 November 2017 | None | Elevated |
4 | Kukatpally | 29 November 2017 | None | Elevated |
5 | Balanagar | 29 November 2017 | None | Elevated |
6 | Moosapet | 29 November 2017 | None | Elevated |
7 | Bharat Nagar | 29 November 2017 | None | Elevated |
8 | Erragadda | 29 November 2017 | None | Elevated |
9 | ESI Hospital | 29 November 2017 | None | Elevated |
10 | S.R Nagar | 29 November 2017 | None | Elevated |
11 | Ameerpet | 29 November 2017 | style="background:#Шаблон:Rcr; text-align: center"| Blue Line | Elevated |
12 | Punjagutta | 24 September 2018 | None | Elevated |
13 | Irrum Manzil | 24 September 2018 | None | Elevated |
14 | Khairatabad | 24 September 2018 | None | Elevated |
15 | Lakdi-ka-pul | 24 September 2018 | None | Elevated |
16 | Assembly | 24 September 2018 | None | Elevated |
17 | Nampally | 24 September 2018 | None | Elevated |
18 | Gandhi Bhavan | 24 September 2018 | None | Elevated |
19 | Osmania Medical College | 24 September 2018 | None | Elevated |
20 | M.G. Bus Station | 24 September 2018 | style="background:#Шаблон:Rcr; text-align: center"| Green Line | Elevated |
21 | Malakpet | 24 September 2018 | None | Elevated |
22 | New Market | 24 September 2018 | None | Elevated |
23 | Musarambagh | 24 September 2018 | None | Elevated |
24 | Dilsukhnagar | 24 September 2018 | None | Elevated |
25 | Chaitanyapuri | 24 September 2018 | None | Elevated |
26 | Victoria Memorial | 24 September 2018 | None | Elevated |
27 | L.B. Nagar | 24 September 2018 | None | Elevated |
Green Line: JBS–Falaknuma
Шаблон:Main
Route length – Шаблон:Cvt
Number of stations (all elevated) – 16
Link to other corridors
- At Mahatma Gandhi Bus Station – connecting corridors 2 and 1
# | Station Name | Opened | Connections | Alignment |
---|---|---|---|---|
1 | JBS Parade Ground | 7 February 2020 | None | Elevated |
2 | Parade Ground | 7 February 2020 | style="background:#Шаблон:Rcr; text-align: center"| Blue Line | Elevated |
3 | Secunderabad West | 7 February 2020 | None | Elevated |
4 | Gandhi Hospital | 7 February 2020 | None | Elevated |
5 | Musheerabad | 7 February 2020 | None | Elevated |
6 | R.T.C. Cross Roads | 7 February 2020 | None | Elevated |
7 | Chikkadpally | 7 February 2020 | None | Elevated |
8 | Narayanguda | 7 February 2020 | None | Elevated |
9 | Sultan Bazaar | 7 February 2020 | None | Elevated |
10 | M.G. Bus Station | 7 February 2020 | style="background:#Шаблон:Rcr; text-align: center"| Red Line | Elevated |
11 | Salarjung Museum | TBA | None | Elevated |
12 | Charminar | TBA | None | Elevated |
13 | Shah-Ali-Banda | TBA | None | Elevated |
14 | Shamsherganj | TBA | None | Elevated |
15 | Jungametta | TBA | None | Elevated |
16 | Falaknuma | TBA | None | Elevated |
Blue Line: Raidurg-Nagole
Шаблон:Main
Route length – Шаблон:Cvt
Number of stations (all elevated) – 23
Link to other corridors
- At Ameerpet – connecting corridors 3 and 1
- At Parade Ground – connecting corridors 3 and 2
# | Station Name | Opened | Connections | Alignment |
---|---|---|---|---|
1 | Raidurg | 29 November 2019 | None | Elevated |
2 | HITEC City | 20 March 2019 | None | Elevated |
3 | Durgam Cheruvu | 20 March 2019 | None | Elevated |
4 | Madhapur | 13 April 2019 | None | Elevated |
5 | Peddamma Gudi | 30 March 2019 | None | Elevated |
6 | Jubilee Hills Check Post | 18 May 2019 | None | Elevated |
7 | Jubilee Hills Road No. 5 | 20 March 2019 | None | Elevated |
8 | Yousufguda | 20 March 2019 | None | Elevated |
9 | Madhura Nagar | 20 March 2019 | None | Elevated |
10 | Ameerpet | 29 November 2017 | style="background:#Шаблон:Rcr; text-align: center"| Red Line | Elevated |
11 | Begumpet | 29 November 2017 | None | Elevated |
12 | Prakash Nagar | 29 November 2017 | None | Elevated |
13 | Rasoolpura | 29 November 2017 | None | Elevated |
14 | Paradise | 29 November 2017 | None | Elevated |
15 | Parade Ground | 29 November 2017 | style="background:#Шаблон:Rcr; text-align: center"| Green Line | Elevated |
16 | Secunderabad East | 29 November 2017 | None | Elevated |
17 | Mettuguda | 29 November 2017 | None | Elevated |
18 | Tarnaka | 29 November 2017 | None | Elevated |
19 | Habsiguda | 29 November 2017 | None | Elevated |
20 | NGRI | 29 November 2017 | None | Elevated |
21 | Stadium | 29 November 2017 | None | Elevated |
22 | Uppal | 29 November 2017 | None | Elevated |
23 | Nagole | 29 November 2017 | None | Elevated |
Finances
The Hyderabad metro is a Public–private partnership project, the total cost of this transport systems is Шаблон:USD 3.07 billion which is shared by both Larsen & Toubro (90%) Government of Telangana (10%).[138] In July 2022, L&T Metro Rail Hyderabad Limited came up with a unique concept of ‘Office Bubbles’ wherein it will offer remote, co-working spaces as part of its Transit-oriented development (ToD). The L&T Hyderabad Metro organisation is offering 1,750 sq. ft. space with two units each in 49 Metro stations across the three corridors and another 5,000-30,000 sq. ft. in eight other Metro stations.[139] Focusing on IT companies, Office Bubbles concept offers Spoke–hub distribution paradigm.[140]
In Hyderabad Metro, 40 per cent of the retail space was sold even before the metro stations were built to generate non-fare revenue.[141] L&TMRHL built real- estate projects like Next Galleria malls in Panjagutta, Irrum Manzil, Hitech City and Musarambagh with skywalks,[142] for generating non-fare revenues under Transit-oriented development (TOD).[12][143][144] In 2019, Hyderabad Metro started a semi-naming policy of metro stations, awarded through an open e-tendering process, to generate non-fare revenues.Шаблон:Citation needed
Depots
Hyderabad Metro currently has 2 operational depots.[145] Miyapur and Uppal depot land is 100 acres each.[146][147] The proposed Falaknuma depot will be constructed in 17 acres.
Hyderabad Metro | ||||
---|---|---|---|---|
Depots | ||||
Line No. | Line Name | Number of Depots | Location | Opening Date |
1 | style="background:#Шаблон:Rcr; text-align: center;" | Red Line | 1 | Miyapur Depot, Near Calvary Temple, Nadigada Tanda, Miyapur, Hyderabad, Telangana | 28 November 2017 |
2 | style="background:#Шаблон:Rcr; text-align: center;" | Blue Line | 1 | Uppal Metro Depot, Nagole Rd, Laxmi Narayan Nagar Colony, Uppal, Hyderabad, Telangana | 28 November 2017 |
3 | style="background:#Шаблон:Rcr; text-align: center;" | Green Line | 1 | Falaknuma | 8 February 2020 |
Ridership
The Metro has opened to overwhelming response, with over 200,000 people using it on Day 1.[148] On the first Sunday of operations, the Metro was used by 240,000 people.[149] As of 2020, the daily ridership is about 490,000. Although there was hiccups in the beginning of operations in 2017 with meager ridership of 100,000 per day, opening the new lines to LB Nagar and Hi-Tech city in 2018–19, ridership has surged and reached milestones from 2 to 4 lakhs in very short duration.[150]
Trains are initially being operated at a frequency of 3 minutes in very peak hours and every 5 minutes in peak hours (between Miyapur-LB Nagar) and 4 minutes in peak hours (between Hi-Tec City/ Ameerpet-Nagole),[151] though maximum achievable frequency is every 90 seconds. Similarly, three-car trains are being used currently, though it is planned to use six-car trains in the future.[152]
In December 2017, Hyderabad Metro Rail launched its mobile app, TSavaari.[153][154] Hyderabad Metro timings are available on T-Savari app.[155] Ola Cabs and Uber tied up its services with app.[156]
In May 2022, Hyderabad Metro Managing Director N.V.S. Reddy ruled out possibility of attaching one single or double coach to three-coach train sets.[157][158] Each three-coach train can take between 900-1,000 passengers per trip[159] and the project has been envisaged in such a manner that another three-coach set rake can be attached to make them into six-coach trains with the stations/depots too already planned for the increased length of the trains.[160][161] L&T Metro Rail has been using 53 train sets of three coaches each with four three-coach sets under repair or maintenance undertaken using special software based on Internet of Things. Hyderabad Metro Rail crossed 100 million cumulative ridership milestone in just 671 days.Шаблон:Citation needed In February 2023, Hyderabad Metro announced that Folding cycles are allowed on Metro, which are of the size of a 40 kg bag, but only during non-peak hours.[162]
Last-mile connectivity
In order to enhance first and last mile connectivity of Hyderabad Metro Rail, Svida Mobility Pvt Ltd, an urban mobility services startup signed a Memorandum of Understanding (MoU) with the L&T Metro Rail Hyderabad Limited (L&TMRHL) with plans to scale up their feeder vehicle services.[163] Svida offers services via a robust AI-enabled tech platform, which provides the booking of feeder vehicles. Svida Mobility Pvt Ltd is L&TMRHL authorised feeder service provider since 2019.[164] The first and last mile connectivity routes, across seven metro stations - Raidurg, Parade ground, Mettuguda, LB Nagar, Uppal, KPHB and Miyapur- use e-Autos and Tata wingers. On 21 April 2022, Hyderabad metro launched its electric auto services in collaboration with AI-enabled ride-hailing mobility platform MetroRide.[165][166] The services were launched at two metro stations - Parade Grounds and Raidurg Stations.[167][168]
Cost
The initial official estimated cost of the 72 km long Metro project stood at Шаблон:INRConvert. The State Government decided to bear 10% of it, while L&T was to bear the remaining 90% of the cost.[169][170] The construction work which was supposed to commence on 3 March 2011 commenced in 2012. In March 2012, the cost of the project was revised upwards to Шаблон:INRConvert.[171] This has been further revised upwards to Шаблон:INRConvert (as of November 2017).[18]
Infrastructure
The 71.3 km standard-gauge network will feature ballastless track throughout and will be electrified at 25 kV AC 50 Hz. An operations control centre and depot are constructed at Uppal. At some places, a flyover, underpass and metro has been constructed at the same place, as part of Strategic road development plan (SRDP).[172]
CBTC Technology
At the end of 2012, L&T Metro Rail awarded Thales a Шаблон:INR7.4 billion ($US 134m) contract to provide CBTC and integrated telecommunications and supervision systems on all three lines. Thales Group supplied its SelTrac Communications-based train control (CBTC) technology,[173] and trains initially run in automatic train operation mode with minimum headways of 90 seconds, although the system will support eventual migration to unattended train operation (UTO).[174]
Rolling stock
On 12 September 2012, Larsen and Toubro Metro Rail Hyderabad Ltd (LTMRHL) announced that it has awarded tender for supply of rolling stock to Hyundai Rotem.[175][176] The Шаблон:INRConvert tender is for 57 trains consisting of 171 cars which will be delivered in phases at least 9 months before the commencement of each stage.[177][178] On 2 October 2013, LTMRHL unveiled its train car for Hyderabad Metro. A model coach which is half the size of the actual coach, was on public display at Necklace Road on the banks of Hussain Sagar in the heart of Hyderabad.[179] The trains will be 3.2m wide and 4m high.[180] There will be 4 doors on each side of each coach.[180]
On 10 April 2014, the first metro train for HMR rolled out of Hyundai Rotem factory at Changwon in South Korea and reached Hyderabad in May 2014.[181] On 31 December 2014, Hyderabad Metro Rail successfully conducted a training run in Automatic Train Operation (ATO) mode for the first time between Nagole and Mettuguda.[182] In February 2022, Hyderabad Metro became India's first metro rail to introduce ozone-based sanitisation of its train coaches.[183] Hyderabad Metro rakes regenerate power using the regenerative braking system.[184]
Ticketing and recharge
The L&T Hyderabad project has an automated ticketing system with features such as contactless smart card based ticketing, slim automatic gates, payment by cash and credit/debit card, passenger operated ticket vending machine and provision of common ticketing system. It also have a provision of NFC-based technology to enable usage of mobile phones as fare media and high performance machine to avoid long queues.[185] Hyderabad Metro Rail smart card acts as a virtual wallet that facilitates seamless travel. A smart card can be purchased from a ticketing office at any Hyderabad Metro station or through TSavaari App. A smart card can be recharged for a minimum amount of Шаблон:INR 50 and maximum amount of Шаблон:INR 3000. The smart card can be recharged through TSavaari App, HMR Passenger website (www.ltmetro.com), or Paytm App. There is 10% discount on all trips made through smart card.[186] In December 2019, Hyderabad Metro started cashless QR (Quick Response) code payment option for e-tickets through MakeMyTrip and Goibibo.[187][188] In October 2022, Hyderabad Metro became the first Metro rail in the country to launch an end-to-end fully digital payment-enabled Metro ticket booking through the WhatsApp e-ticketing facility.[189][190]
Samsung Data Systems India, a subsidiary of South Korean firm Samsung, has been awarded the automatic fare collection system package for the L&T metro rail project. The package involves design, manufacture, supply, installation, testing and commissioning of the system.[185][191] Official ticket prices were announced on 25 November 2017. The base fare is Шаблон:INR10 for up to 2 km.Шаблон:Citation needed
Slab | Distance (km) | Metro Fare (Шаблон:INR) |
---|---|---|
1 | 0 - 2 | 10 |
2 | 2 - 4 | 15 |
3 | 4 - 6 | 25 |
4 | 6 - 8 | 30 |
5 | 8 - 10 | 35 |
6 | 10 - 14 | 40 |
7 | 14 - 18 | 45 |
8 | 18 - 22 | 50 |
9 | 22 - 26 | 55 |
10 | > 26 | 60 |
Awards and nominations
The HMR project was showcased as one of the top 100 strategic global infrastructure projects at the Global Infrastructure Leadership Forum held in New York during February–March 2013.[192][193]
L&T Metro Rail Hyderabad Limited (LTMRHL) was conferred the SAP ACE Award 2015 in the 'Strategic HR and Talent Management'[194] category.
In 2018 the Rasoolpura, Paradise and Prakash Nagar Metro stations were awarded the Indian Green Building Council's (IGBC) Green MRTS Platinum Award.[195]
Hyderabad Metro was adjudged as the Best Urban Mass Transit Project by the Government of India in November 2018.[196]
In October 2022, three metro stations of Hyderabad Metro- Durgam Cheruvu , Punjagutta and LB Nagar were awarded Indian Green Building Council (IGBC) Green MRTS Certification with the highest platinum rating under elevated stations category.[197] With this, Hyderabad Metro Rail has 23 metro stations certified with the IGBC Platinum rating.[198]
In March 2024, a study done by Indian School of Business team on Hyderabad Metro Rail project execution was published as a case study in Stanford University for the benefit of management practitioners.[199][200][201]
In popular culture
- 2018 Telugu film Devadas starring Nani and Rashmika Mandanna, was the first film to be shot in Hyderabad Metro.[202][203]
- Some scenes of 2021 Telugu films- Vakeel Saab starring Pawan Kalyan and Nivetha Thomas, and Ek Mini Katha starring Santosh Shoban and Kavya Thapar were also shot in Hyderabad Metro.[204][205]
- In June 2022, a scene from the upcoming Indian science fiction film Kalki 2898 AD, starring Amitabh Bachchan was shot at Raidurg Metro Station.[206] Some scenes of the film 18 Pages were also shot in Hyderabad Metro.
- Many scenes of the 2023 released Hindi film 8 A.M. Metro and Telugu film Kushi were shot in Hyderabad Metro.
Network map
See also
- Transport in Hyderabad
- Hyderabad Multi-Modal Transport System
- Rajiv Gandhi International Airport
- Namma Metro
- List of metro systems
References
External links
Шаблон:Commons category Шаблон:Wikivoyage Шаблон:Rapid transit OSM map
Шаблон:Larsen & Toubro Шаблон:Hyderabad Metro Шаблон:Rapid transit in India Шаблон:Rapid transit in Asia Шаблон:Keolis Шаблон:Portal bar
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ 3,0 3,1 Шаблон:Cite news
- ↑ 4,0 4,1 Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ 12,0 12,1 Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ 18,0 18,1 Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ The Hindu Business Line, Hyderabad 23 January 2018
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Hyderabad: 2-decker marvel in Metro-3
- ↑ Шаблон:Cite web
- ↑ 117,0 117,1 Шаблон:Cite web
- ↑ 118,0 118,1 Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite webШаблон:Dead linkШаблон:Cbignore
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ 180,0 180,1 Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ 185,0 185,1 Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite news
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- ↑ Шаблон:Cite web
- Английская Википедия
- Страницы с неработающими файловыми ссылками
- Hyderabad Metro
- Keolis
- Transport in Hyderabad, India
- Rail transport in Telangana
- Standard gauge railways in India
- 2017 establishments in Telangana
- Public–private partnership projects in India
- Страницы, где используется шаблон "Навигационная таблица/Телепорт"
- Страницы с телепортом
- Википедия
- Статья из Википедии
- Статья из Английской Википедии