Английская Википедия:INS Vikrant (2013)

Материал из Онлайн справочника
Перейти к навигацииПерейти к поиску

Шаблон:Short description Шаблон:Other ships Шаблон:Use Indian English Шаблон:Use dmy dates

Шаблон:Infobox ship imageШаблон:Infobox ship careerШаблон:Infobox ship characteristics

INS Vikrant (Шаблон:IPA-hi)[1] is an aircraft carrier in service with Indian Navy. The carrier is India's fourth carrier and the first to be built in India. It was constructed by the Cochin Shipyard Limited (CSL) in Kochi, Kerala. The namesake Vikrant is a tribute to India's first aircraft carrier INS Vikrant (1961). Vikrant means "courageous" in Sanskrit.[2] The motto of the ship, "जयेम सम् युधिस्पृधः" (Sanskrit), means "I defeat those who dare to challenge me" (English).

Work on the ship's design began in 1999. The keel was laid in 2009. The carrier was floated out of dry dock in December 2011[3] and launched in August 2013.[4] Basin trials were completed in December 2020,[5] and sea trials started in August 2021.[6] Its commissioning ceremony was held on 2 September 2022.[7] Aircraft flight trials will be completed in 2023.[6][8] The total cost of the project is approximately Шаблон:INRConvert at the time of first sea trials.[9][10]

Vikrant's air group can consist up to 26 Rafale M fighters[11] and up to 4 Kamov Ka-31,[12] or 2 HAL Dhruv NUH[13] or 4 MH-60R[14] helicopters.[10] It is Шаблон:Convert in length, with a top speed of Шаблон:Convert and endurance of Шаблон:Convert. The ship has 2,300 compartments manned by 1,700 seamen. It has a hospital complex, cabins for female officers, Шаблон:Convert of corridors, and eight generators capable of lighting up a city of 2 million people.[15]

Background

In 1999, Defence Minister George Fernandes authorised the development and construction of an aircraft carrier, INS Vikrant, under the Project 71 Air Defence Ship (ADS).[16] By that time, given the ageing Sea Harrier fleet, the letter of intent called for a carrier that would carry more modern jet fighters. In 2001, Cochin Shipyard Limited (CSL) released a graphic illustration showing a Шаблон:Convert STOBAR (Short Take-Off But Arrested Recovery) design with a pronounced ski jump.Шаблон:Citation needed

The aircraft carrier project received formal government approval in January 2003. By then, design updates called for a Шаблон:Convert carrier to operate the Mikoyan MiG-29K. India opted for a three-carrier fleet consisting of one carrier battle group stationed on each seaboard, and a third carrier held in reserve, in order to continuously protect both its flanks, to protect economic interests and mercantile traffic, and to provide humanitarian platforms in times of disasters, since a carrier can provide a self-generating supply of fresh water, medical assistance or engineering expertise to populations in need for assistance.[17]

In August 2006, Chief of the Naval Staff Admiral Arun Prakash stated that the designation for the vessel had been changed from Air Defence Ship (ADS) to Indigenous Aircraft Carrier (IAC). The euphemistic ADS had been adopted in planning stages to ward off concerns about a naval build-up.Шаблон:Citation needed Final revisions to the design increased the displacement of the carrier from 37,500 tons to over 45,000 tons. The length of the ship increased from Шаблон:Convert to Шаблон:Convert.[18]

Repeat Order

In addition to the already proposed INS Vishal, the Indian Navy is also looking for another Vikrant class aircraft carrier, IAC-2, with similar dimensions and capabalities. As of March 2024, Indian Navy has been submitted the proposal to acquire another Aircraft Carrier to Ministry of Defence. IAC-2 will have an increased indigenous content than INS Vikrant (IAC-1). The major components which will be indigenised includes arresting gear system, restraining gear used to launch aircraft and Precision Approach Radar.[19][20]

Design

Файл:INS Vikrant CGI.svg
A schematic diagram of INS Vikrant

INS Vikrant is Шаблон:Convert long and Шаблон:Convert wide, and displaces about Шаблон:Convert.[21] It features a STOBAR configuration.[22] It can carry an air group of up to thirty-six aircraft,[23] including 26 fixed-wing combat aircraft,[24] and a mix of Dhruv MK-III, Sikorsky MH-60R and Kamov Ka-31 helicopters. The Ka-31 will fulfil the airborne early warning (AEW) role, MH-60R will provide anti-surface and anti-submarine warfare (ASW) capabilities,[25] and Dhruv will be used mainly for search and rescue operations.[26]

Vikrant is powered by four General Electric LM2500+ gas turbines on two shafts, generating over 80 megawatts (110,000 hp) of power. The gearboxes for the carriers were designed and supplied by Elecon Engineering.[3][27][28]

The ship's combat management system (CMS) was developed by Tata Advanced Systems.[29] It is the first CMS developed by a private company for the Indian Navy and was handed over to the Navy on 28 March 2019.[30][31]

Carrier air group

Файл:Maiden landing of MiG-29K onboard Vikrant (R11).webm
The maiden landing of a MiG-29K onboard INS Vikrant (R11)

Earlier, the Indian Navy considered fielding MiG-29K,[32] and LCA Navy on Vikrant.[33] At the same time, in 2009, the then navy Chief Admiral Nirmal Kumar Verma hinted that the Navy was carrying out a concept study for a more capable naval fighter,[33] which turned out to be the HAL TEDBF, unveiled at 2021 Aero India airshow.[34] In June 2012, Flight Global reported that the Indian Navy was considering the purchase of Dassault Rafale M (Naval variant) for Vikrant.[35] The Rafale was by then declared the winner of IAF's MMRCA competition.[36]

In 2016, the Navy announced that the Tejas was overweight for carrier operations, and other alternatives would be looked at.[37][38] In 2017, a request for proposal was issued for 57 "Multi-Role Carrier Borne Fighters",[39] which was later cut down to 26 fighters act as a stop gap measure until the TEDBF is developed.[40] In December 2020, Boeing Defense, Space & Security, in coordination with the United States Navy, demonstrated F/A-18E/F Super Hornet's capability to operate from STOBAR carrier.[41][42][43]

Файл:HAL Dhruv onboard INS Vikrant (R11) during sea trials.jpg
HAL Dhruv onboard Vikrant during sea trials

In 2022, the Indian Navy began testing the Rafale M and Boeing F/A-18E/F Super Hornet at a shore-based test facility at INS Hansa in Goa.[44][45][46][47] The Navy started the fixed wing aviation trials with Tejas Naval variant. This to be followed by MiG-29K trials.[48]

On 6 February 2023, two arrested landings were made by MiG-29Ks, and also by a HAL Tejas (Naval Variant).[49]

Ultimately, the Indian military chose the Rafale M from France for compatibility with its logistics system.[50] During his visit on 14 July 2023, PM Narendra Modi will be the guest of honor at the Bastille Day parade in France, during which India is expected to announce the purchase of 24 to 30 Rafale fighter jets.[51][52] The Indian government announced the selection of the naval variant of Rafale jets to equip the Indian Navy with the latest-generation fighter, Dassault Aviation said on July 15.[53]

The prototype of the TEDBF is to be readied by 2026 and its production is to begin by 2032. Naval Tejas being a technology demonstrator development of niche technology for deck based fighter operations, paving the way for TEDBF.[40]

Construction

Файл:Indigenous Aircrafft Carrier-1 maiden sea voyage.webm
IAC-1 on its maiden sea voyage.

Vikrant is the first aircraft carrier to be designed by the Warship Design Bureau (formerly Directorate of Naval Design) of the Indian Navy and the first warship to be built by Cochin Shipyard. Its construction involved participation of a large number of private and public firms.

The Defence Metallurgical Research Laboratory (DMRL) and Steel Authority of India Limited (SAIL) created facilities to manufacture the DMR 249 grade steel in India.[3][54] Reportedly, Шаблон:Convert of three types of special steel for the hull, flight deck and floor compartments were manufactured at the Bokaro Steel Plant, Jharkhand, Bhilai Steel Plant, Chhattisgarh and Rourkela Steel Plant, Odisha. Due to this, Vikrant is the first ship of the Indian Navy to be built completely using domestically produced steel.[55]

The main switch board, steering gear and water tight hatches have been manufactured by Larsen & Toubro in Mumbai and Talegaon; high-capacity air conditioning and refrigeration systems have been manufactured in Kirloskar Group's plants in Pune; most pumps have been supplied by Best and Crompton; Bharat Heavy Electricals (BHEL) supplied the Integrated Platform Management System (IPMS), which is being installed by Avio, an Italian company; the gear box was supplied by Elecon Engineering; and the electrical cables are being supplied by Nicco Industries.[56] Fincantieri provided consultancy for the propulsion package while Russia's Nevskoye Design Bureau designed the aviation complex.[57]

The keel for Vikrant was laid by Defence Minister A.K. Antony at the Cochin Shipyard on 28 February 2009.[58][59] The ship uses modular construction, with 874 blocks joined for the hull. By the time the keel was laid, 423 blocks weighing over 8,000 tons had been completed.[60] In August 2011, the Defence Ministry reported to the Lok Sabha that 75% of the construction work for the hull of the lead carrier had been completed and the carrier would be first launched in December 2011, following which further works would be completed until commissioning.[61][62] On 29 December 2011, the completed hull of the carrier was first floated out of its dry dock at CSL, with its displacement at over Шаблон:Convert.[27] Interior works and fittings on the hull would be carried out until the second half of 2012, when it would again be dry-docked for integration with its propulsion and power generation systems.[63][3] By late 2012, work commenced for the next stage of construction, which included the installation of the integrated propulsion system, the superstructure, the upper decks, the cabling, sensors and weapons.[64]

Launch

Файл:ഐ.എൻ.എസ്. വിക്രാന്ത് കൊച്ചി കപ്പൽ ശാലയിൽ ഓഗസ്റ്റ് 2013.jpg
INS Vikrant during its launch in August 2013

In July 2013, Defence Minister Antony announced that Vikrant would be launched on 12 August at the Cochin Shipyard. The ship was launched by his wife, Elizabeth Antony, on 12 August 2013.[65]

According to Admiral Robin Dhowan, about 83% of the fabrication work and 75% of the construction work had been completed at the time of launching. He said that 90% of the body work of the aircraft carrier had been designed and made in India, about 50% of the propulsion system, and about 30% of its weaponry. He also said that the ship would be equipped with a long range missile system with multi-function radar and a close-in weapon system (CIWS).[66] After the launch, Vikrant would be re-docked for the second phase of construction, in which the ship would be fitted with various weapons and sensors, and the propulsion system, flight deck and the aircraft complex would be integrated.[56]

Undocking and fitting-out

Файл:INS Vikrant being undocked at the Cochin Shipyard Limited in 2015 (08).jpg
INS Vikrant during its undocking in June 2015

Vikrant was undocked on 10 June 2015 after the completion of structural work. Cabling, piping, heat and ventilation works were scheduled to be completed by 2017 with sea trials to begin thereafter.[67] By October 2015, the construction of the hull was close to 98 percent complete, with flight deck construction underway.[68] The installation of machinery, piping and the propeller shafts was in progress by January 2016; it was reported, however, that there were delays in the delivery of equipment from Russia for the carrier's aviation complex.[69] By May 2017, the carrier's fitting-out was 62% complete, with trials of the auxiliary systems scheduled by late 2017.[70]

In February 2020, all major structural and outfitting work was declared complete.[71]

Harbour and sea trials

Файл:Basin Trials of Indigenous Aircraft Carrier 2.jpg
Basin trials of the aircraft carrier.

On 31 October 2019, Cochin Shipyard received a Шаблон:INRConvert contract for the Phase-III of the project.[72] This contract included funds for the harbour trials, sea trials and support for the ship during its weapons and aviation trials after its delivery.[73] In December 2019, it was reported the engines had been switched on.[74] By September 2020, Vikrant had completed harbour trials while the basin trials started from October 2020 to check propulsion, electric transmission and shafting systems.[75] On 30 November 2020, the basin trials were completed, paving the way for sea trials, the final phase of the IAC-I project.[76][77]

Файл:IAC-1 Vikrant going for its maiden sea trials.jpg
A Westland WS-61 Sea King approaches Vikrant while on sea trials

In April 2021, it was reported work had begun to integrate the long-range surface-to-air missile (LRSAM) onboard Vikrant.[78][79][80] On 15 June 2021, Vikrant was moved to the Ernakulam Wharf in Kochi, Kerala.[81] On 4 August 2021, sea trials finally began.[82] The first phase of the sea trials was successfully completed on 8 August 2021.[83] The second phase of the trials was conducted on 24 October 2021,[84] followed by the third phase from 9–17 January 2022,[85][86][87] both of which were completed successfully.[88] On 10 July, the fourth and final phase of the sea trials was successfully completed. This phase involved integrated trials of most of the equipment and systems aboard Vikrant, including portions of the Aviation Facilities Complex.[89] On 26 May 2023 Indian built Mikoyan MiG-29K successfully landed on its deck during night sea trials lauding praise from defense ministry for Navy's dependence on Atmanirbhar Bharat.[90]

Completion and commissioning

Файл:The Prime Minister, Shri Narendra Modi commissions the first indigenous aircraft carrier as INS Vikrant, in Kochi, Kerela on September 02, 2022 (2).jpg
Prime Minister Narendra Modi commissioned INS Vikrant on 2 September 2022 in Kochi, Kerala.

Prime Minister Narendra Modi commissioned INS Vikrant on 2 September 2022 in a grand ceremony at Cochin Shipyard.[7][91] Earlier, INS Vikrant was delivered to the Indian Navy on 28 July 2022.[92] Flight trials of its aircraft complement are expected to be completed by mid-2023, after which the ship will be fully operational.[6] In March 2020, it was revealed that after its commissioning, the Navy will deploy Vikrant at Larsen & Toubro's shipyard in Kattupalli near Chennai. This was done as the planned naval base in Rambilli near Vishakhapatnam was not ready yet.[93]

The Navy wants to lease a 260 m berth at Kattupalli shipyard for 8 years between 2022 and 2030 for interim berthing of the ship, by which time the naval base at Rambilli is expected to be available.[93] On 6 February 2023, the naval variant of the Tejas became the first fixed wing fighter to launch from and recover to Vikrant.[94] On 22 March 2023, the Vice Chief of Navy Staff, Vice Admiral SN Ghormade, returned the bell originally placed on the previous Шаблон:INS to Commodore Vidhyadhar Harke, the new ship's first commanding officer. In 1997, the bell of the decommissioned namesake ship was placed at the residence of Indian Navy Vice Chief, 5 Motilal Nehru Marg, New Delhi.[95]

Файл:LCA Tejas maiden landing onboard INS Vikrant (R11).webm
LCA Tejas maiden landing onboard INS Vikrant (R11)

Following the Formal Commissioning of Vikrant, a proposal was made to build another IAC class carrier before INS Vishal . By November 2023 a ₹400 Billion worth proposal for a new carrier was on track to be approved by the Defense Acquisition Council — the country's top defense decision-making body headed by defense minister, Rajnath Singh.[96][97]

The new carrier, which can hold at least 28 fighter jets and helicopters will displace 45,000 tons of water and will be flying the French Rafale jets initially, but will fly HAL TEDBF fighters in 2030s.[98]

Commanding officers

Name Took command Left command Notes
Captain Vidhyadhar Harke Шаблон:Small 7 May 2021 31 December 2023 First CO of Vikrant. Current CSO (Ops), Western Naval Command.[99]
Captain Birendra S Bains Шаблон:Small 31 December 2023 Present Commissioning CO of Шаблон:Ship.[100][101]

Project delays

The construction plan originally called for the carrier to be launched in 2010,[102] sea trials to commence in 2013, and to be commissioned in 2016.[103][104] However, the project experienced some delays such as delay in the delivery of main gearboxes, aviation equipments etc., and cost overrun.[105] The supplier of gearboxes, Elecon, attributed it to technical complexities due to the length of the propulsion shafts.[106]

A part of the blame for the delay in delivery of Vikrant was attributed to the delay in the supply of aviation equipment from Russia. In response to a question in the Rajya Sabha, Sripad Naik, the Minister of State for Defence, stated: "Ship's targeted delivery was affected due to delay in supply of aviation equipment from Russia".[107] Later due to the Covid-19 pandemic, sea trials of the carrier were further postponed to late 2020,[108] but eventually began in August 2021. The carrier was commissioned on 2 September 2022.[109][110][111]

Gallery

Шаблон:Gallery

See also

References

Шаблон:Reflist

External links

Шаблон:Commons category

Шаблон:Indian Navy aircraft carriers Шаблон:Ship classes of the Indian Navy Шаблон:Aircraft carrier classes in service

  1. Шаблон:Cite web
  2. Шаблон:Cite news
  3. 3,0 3,1 3,2 3,3 Шаблон:Cite news
  4. Шаблон:Cite web
  5. Шаблон:Cite web
  6. 6,0 6,1 6,2 Шаблон:Cite web
  7. 7,0 7,1 Шаблон:Cite news
  8. Шаблон:Cite news
  9. Ошибка цитирования Неверный тег <ref>; для сносок vikrant не указан текст
  10. 10,0 10,1 Ошибка цитирования Неверный тег <ref>; для сносок msn не указан текст
  11. Шаблон:Cite web
  12. Шаблон:Cite web
  13. Шаблон:Cite web
  14. Шаблон:Cite web
  15. Шаблон:Cite web
  16. Шаблон:Cite web
  17. Шаблон:Cite web
  18. Шаблон:Cite web
  19. Шаблон:Cite web
  20. Шаблон:Cite web
  21. Шаблон:Cite web
  22. Шаблон:Cite news
  23. Шаблон:Cite web
  24. Шаблон:Cite web
  25. Шаблон:Cite web
  26. Шаблон:Cite web
  27. 27,0 27,1 Шаблон:Cite news
  28. Шаблон:Cite news
  29. Ошибка цитирования Неверный тег <ref>; для сносок theprint01 не указан текст
  30. Шаблон:Cite web
  31. Шаблон:Cite web
  32. Шаблон:Cite news
  33. 33,0 33,1 Шаблон:Cite web
  34. Шаблон:Cite web
  35. Шаблон:Cite news
  36. Шаблон:Cite news
  37. Шаблон:Cite web
  38. Шаблон:Cite web
  39. Шаблон:Cite web
  40. 40,0 40,1 Шаблон:Cite web
  41. Шаблон:Cite news
  42. Шаблон:Cite web
  43. Шаблон:Cite web
  44. Шаблон:Cite web
  45. Шаблон:Cite web
  46. Шаблон:Cite web
  47. Шаблон:Cite web
  48. Шаблон:Cite news
  49. Шаблон:Cite web
  50. Шаблон:Cite web
  51. Шаблон:Cite web
  52. Шаблон:Cite news
  53. Ошибка цитирования Неверный тег <ref>; для сносок TH не указан текст
  54. Шаблон:Cite news
  55. Шаблон:Cite news
  56. 56,0 56,1 Шаблон:Cite news
  57. Шаблон:Cite news
  58. Шаблон:Cite web
  59. Шаблон:Cite web
  60. Шаблон:Cite news
  61. Шаблон:Cite news
  62. Шаблон:Cite web
  63. Шаблон:Cite web
  64. Шаблон:Cite news
  65. Шаблон:Cite news
  66. Шаблон:Cite news
  67. Шаблон:Cite web
  68. Шаблон:Cite web
  69. Шаблон:Cite web
  70. Шаблон:Cite web
  71. Шаблон:Cite news
  72. Шаблон:Cite web
  73. Шаблон:Cite news
  74. Шаблон:Cite news
  75. Шаблон:Cite web
  76. Шаблон:Cite tweet
  77. Шаблон:Cite web
  78. Шаблон:Cite web
  79. Шаблон:Cite web
  80. Шаблон:Cite web
  81. Шаблон:Cite web
  82. Шаблон:Cite web
  83. Шаблон:Cite web
  84. Шаблон:Cite news
  85. Шаблон:Cite web
  86. Шаблон:Cite news
  87. Шаблон:Cite news
  88. Шаблон:Cite news
  89. Шаблон:Cite web
  90. Шаблон:Cite web
  91. Шаблон:Cite news
  92. Шаблон:Cite web
  93. 93,0 93,1 Шаблон:Cite web
  94. Шаблон:Cite web
  95. Шаблон:Cite web
  96. Шаблон:Cite news
  97. Шаблон:Cite web
  98. Шаблон:Cite web
  99. Шаблон:Cite web
  100. Шаблон:Cite tweet
  101. Шаблон:Cite news
  102. Шаблон:Cite web
  103. Шаблон:Cite news
  104. Шаблон:Cite web
  105. Шаблон:Cite news
  106. Шаблон:Cite news
  107. Шаблон:Cite web
  108. Шаблон:Cite web
  109. Шаблон:Cite web
  110. Шаблон:Cite web
  111. Шаблон:Cite web